Air Tightness: A
general overview to testing and design
1.0 Key Principles
1.
Testing procedure is set out in CIBSE TM 23 and the ATTMA TS1
2.
A air tightness test involves sealing all ‘normal’ gaps such as vents and
pressurising or depressurising the building. The level of fanpower required to
maintain the pressure differential indicates the ‘leakiness’ or ‘permeability’
of the building.
3.
Air tightness/air leakage tests are typically followed by an air leakage/air
tightness audit (using smoke pencils, for example) to expose and make visible
the various air leakage routes.
4.
Where projects comprise large quantities of a single component, component
testing in the laboratory may be appropriate as well as on site element
testing.
2.0 Climatic conditions
As
mentioned in Chapter 1, the raised pressure differential of 50 Pascals created
during an airtightness test is quite small. Whilst this is adequate to overcome
most of the common pressure differential anomalies, such a small differential
is vulnerable to larger pressure differences created by climatic conditions.
Air
leakage tests/air tightness tests require calm days – i.e. a reading on the
Beaufort Scale of 3 or less (3.4 to 5.4 metres per second wind speed at 10 m
above ground) This corresponds to a gentle breeze with leaves and small twigs
in constant motion. In winter conditions, and on exposed sites therefore
testing may not be possible, although it is often possible to make allowances,
so long as these are carefully recorded during the Air leakage tests/air
tightness tests.
3.0 The Test itself
Guidance
on testing buildings for Air leakage /air tightness is contained in CIBSE
Technical Memorandum TM23 Testing Buildings for Airtightness and in BS EN
13829: 2001. All accredited air tightness testers test to the guidelines
contained in the BS EN and within the ATTMA TS1
Essentially
the air tightness/air leakage process is one of pressurising or (less commonly)
de-pressurising the inside of the whole building, and of measuring the rate at
which air needs to be blown or sucked to maintain that pressure differential; a
building suffering from high amounts of air leakage will equalise readily and
require a greater measurable effort to maintain the 50 Pascal differential,
while a air tight building will easily contain the enforced differential and
require little additional input.
The
pressure difference is induced by one or more calibrated fans that are normally
mounted within a suitable doorway. An adjustable door panel system, sealed
around the edges is used which can also be connected to large external fans via
collapsible ductwork if required. The rate of the fan or the volume flow of air
through the fan can be understood as the rate of air entering / escaping
throughout the remainder of the building envelope.
Buildings are air tightness tested/air leakage tested in such a way as to
recreate ‘normal’ conditions. Doors and windows are closed; trickle ventilators
closed, extract fans and such like are closed but not sealed. Internal doors
are wedged open. All of this must be actioned prior to the air leakage test/air
tightness test
If
the building is under construction, Air tightness testing/air leakage testing
can be undertaken during working hours, but sometimes this is not
practical so some scheduling of work needs to be thought through in advance.
With all external doors and windows sealed shut, some work becomes impossible
(such as work with solvents requiring ventilation) and internal trades are
normally ‘sealed in’ for a short time, where they can carry on undisturbed
throughtout the air leakage/air tightness test
In
existing buildings, Air leakage tests/air tightness tests are normally carried
out when the building is unoccupied if possible because of the disruption.
4.0 Air Leakage Audits
The
air leakage test/air tightness test quantifies the rate of air leakage through
the envelope as a whole, but it cannot locate the air leakage paths. Where
remedial work is required therefore, air leakage/air tightness tests are
followed by a range of auditing techniques designed to identify the specific
places where air is leaking.
In
many cases a simple visual inspection may be sufficient – especially if
undertaken by someone with experience of the likely locations of air leakage.
However,
most air leakage routes are difficult or impossible to spot without visual aids
during the air leakage /air tightness test. One common technique is to use
smoke tracers – smoke pencils or smoke machines. These render the air paths
visible in certain situations. The building may be positively pressurised
during the air leakage/air tightness test and the leaks witnessed externally,
or, more usually, negatively pressurised while a smoke pencil is drawn over
likely gaps and defects which become visible as the smoke is sucked inwards.
Another
technique, which has certain advantages and disadvantages compared to smoke
tracing along with an air leakage/air tightness test, is the use of an infrared
camera during a Thermographic test. Used either externally or internally, these
thermographic cameras register the radiant heat levels of surfaces and so are
able to ‘see’ for example, where cold air is cooling the fabric around a gap
internally, or conversely where warm air is escaping and heating the colder
materials on the external face.
To
work effectively, there needs to be a recognisable difference between the
internal and external ambient temperature, so before any heating has been
installed and on a warm summer’s day thermography testing may not be effective.
Similarly on warm and sunny days, sunshine on external surfaces can distort the
true situation so it is better on such days to wait until early evening.
Conversely, rain on external surfaces can be equally distorting of the true
thermal situation. However the
Thermographic cameras are useful in identifying problems at high level
or difficult to reach areas, and are also very helpful in identifying other
construction defects such as poorly installed (or non-existent!) insulation
within the fabric.
On
larger commercial buildings, airtightness testing/air leakage testing may be
undertaken at the same time as ‘standard’ ventilation system commissioning and
associated studies, but these are not discussed as part of this guide.
5.0 Component Testing
A
distinct aspect of overall air tightness testing is the individual component
test. This may be undertaken quite separately, in the laboratory or by the
manufacturer of a particular component. Such air tightness sampling tests may
be deemed necessary on a large project where large areas of one particular type
of component, for example curtain walling, are to be specified, Insitu element
testing involves isolating the area within a temporary sealed compartment,
which is then pressurised, and the air leakage related to the area of interest
assessed. In this way sample areas of a building may be air tigtness tested
using smaller fans as required.
5.1 Concrete frame and panel
1 Introduction
As thermal
insulation levels have risen in the last few years the proportion of energy
lost to draughts has increased to the extent that now in some cases around half
of all heat losses are due to air leakage across the building fabric. Given
that approximately half of all energy used in the
The
situation is such that further increasing thermal insulation levels would be
largely unproductive unless air tightness is conscientiously addressed. Air
leakage has been shown to reduce the effectiveness of thermal insulation by up
to 70% and so it is clear that if energy efficiency is to be improved in
buildings, the next efforts will have to focus on air tightness/air leakage
testing.
Many
people make the mistake of thinking that an airtight building is necessarily a
‘stuffy’ building. This is not the case. All buildings have to be ventilated
for health and comfort and airtight buildings are no different. An adequate
ventilation system (which may well include openable windows as well as fans
etc.) has to be planned for every building. The difference will be that a great
deal of unplanned air leakage needs to be stemmed.
The
additional costs of creating an adequately airtight building can be
negligible, but even where costs are increased, these can be more than offset
by a reduction in the capital cost of heating and ventilation equipment, not to
mention the long term savings in energy.
Given that
the vast majority of building stock is existing, a great deal of attention will
need to be given, in the foreseeable future, to remedial works to existing
buildings. This guide specifically includes examples of good and best practice
remedial work in terms of air tightness and shows that such works can offer
substantial benefits without undue disruption or cost.
Air
Pressure Testing hopes to provide practical guidance on how to save energy and
costs and protect building fabric. On the basis that prevention is cheaper and
easier than cure, one purpose of this guide is to enable Designers to design
inherently more robust and durable solutions which avoid costly and time
consuming remedial works on site after a potential air leakage failure
The
general guidance here is firmly focused on the idea of practical design and
detailing, and should be read in conjunction with other guidance on sustainable
design, energy efficiency and air tightness where necessary to provide an
overall design framework. The details provided have been fully costed, tested
and subjected to a Defects Liability insurance assessment. They are offered as
viable alternatives to standard details, and illustrate the possibilities that
exist. It simply remains for you, the reader, to apply them appropriately in
the context of your next project prior to your air leakage test/air tightness
test
Aims of this Guide
• To highlight
benefits of air tightness which include both energy and cost efficiency,
improved comfort and reduced risks of damage to building fabric
• To improve
awareness of the need for air tightness in construction
• To promote detailing and specification
solutions which create airtight and efficient buildings thus reducing the need
for remedial works after air leakage failure- ‘prevention rather than cure’
• To show that
new build and remedial air tightness are achievable without undue cost
penalties to construction works due to multiple air leakage failures
• .and in this
way to help to ‘mainstream’ the good and best practice outlined in the document
Target
audience
This Guide will help all those who wish to improve
the airtightness/air leakage rate and energy efficiency of buildings through
their construction, e.g:
• clients
–building owners and users, principal and specialist contractors, interior
designers architects and technicians, structural engineers, building service
engineers, building surveyors, quantity surveyors/ cost consultants,
maintenance and facilities managers, project managers , planning officers and
building control officers, funding bodies and their professional advisors,
government and non-governmental agencies
How to use
this Guide
This Guide is divided into six sections. The first
two sections provide an overview of the issues surrounding air tightness.
Sections Three, Four and Five describe the requirements for the design process,
the procurement and the air leakage/air tightness testing involved in
designing for airtight buildings.
Section Six provides a number of representative
details which have been optimised in terms of airtightness. These are compared
with standard details for a variety of construction types, and costed. This
section will be primarily of interest to the design team. It should be read in
conjunction with sections Three, Four and Five in particular, as all details
must be placed in a suitable context.
6.0 The Context
Key
Principles
1. Most UK
construction is ‘leaky’ and wastes energy and money. Building airtight
buildings can save energy and money, improve comfort and reduce the risk of
damage to building fabric.
2. Airtight building will
NOT mean ‘stuffy’ buildings. Good ventilation is vital for health and comfort -
it is the UNPLANNED leakage of air that we are aiming to stem.
3. Legislation
is slowly catching up with best practice in Scotland, the UK and elsewhere and
we can expect a greater emphasis on airtightness in all types of construction
in due course.
4. Good and Best Practice
Targets of air tightness/air leakage have been set for many types of buildings
and are easily achievable.
6.1 Infiltration, Ventilation and
Airtightness
Air
infiltration (air leakage) is the
uncontrolled flow of air through gaps in the fabric of buildings. It is driven
by wind pressure and temperature differences and as a result is variable,
responding in particular to changes in the weather. Infiltration (air leakage)
levels are strongly affected by both design decisions and construction quality.
Ventilation,
on the other hand, is the intended and controlled ingress and egress of air
through buildings, delivering fresh air, and exhausting stale air in
combination with the designed heating system and humidity control, and the
fabric of the building itself.
Whilst
some unwanted air infiltration (air leakage)
will at times aid comfort levels, it is not reliable and moreover
brings with it a range of significant disadvantages such as high levels of
heat loss, reduction in performance of the installed thermal insulation, poor
comfort, poor controllability and risks to the longevity of the building fabric
itself. It cannot be considered an acceptable alternative to designed
ventilation. Infiltration (air leakage) needs to be reduced as much as possible
if we are to create efficient, controllable, comfortable, healthy and durable
buildings. This can be achieved by delivering airtight buildings that pass the
air tightness/air leakage tests first time.
Air
tightness is a term used to describe the ‘leakiness’ of the building fabric.
An airtight building will resist most unwanted air infiltration (air leakage)
while satisfying its fresh air requirements through a controlled ventilation
strategy. Most existing buildings, even those built recently, are far from
being airtight and because of unwanted air infiltration (air leakage) generate
huge costs to owners and occupants, in environmental, financial and health
terms.
It is
important to emphasise the distinction between infiltration (air leakage) and
ventilation, because while the primary purpose of this document is to show how
buildings can be designed and constructed to be airtight, it is equally
important to stress that good levels of ventilation and a clear ventilation
strategy will be required in every case. As the saying goes: ‘build tight,
ventilate right.’
6.2 Why Build Airtight?
Legislation
At a rather prosaic level, the issue is important
because it is now part of the Building Regulations in England and Wales
concerning non-domestic new buildings over 500 sqm in area, and is likely to
affect a wider range of buildings soon. Whilst the initial targets set for
airtightness of buildings are easy to achieve, it is equally likely that once in
place, those targets will be ratcheted up to create ever more airtight and
efficient buildings in the UK, in line with many of our European neighbours.
Energy and Cost Saving
Typically, the largest heat losses in most
buildings are related to levels of thermal insulation, followed by those
related to infiltration (air
leakage), followed by those related to inefficient plant. Quite
rightly therefore, most efforts to save energy and costs have until recently
been directed at increasing thermal insulation levels. But as these levels
have risen, so the relative contribution of infiltration (air leakage) has increased to the point
where it can represent around half of all heat loss in a building. In highly
insulated buildings, the percentage may be higher.
This is reflected in the fact that total space
heating costs in an airtight building may be as much as 40% less than in a
leaky one
We are at the stage where it is likely that any
further increase in thermal insulation levels would be ineffective until levels
of air tightness in construction have improved considerably.
Space Heating System Reduction
Clearly there is potential to reduce the capacity
of space heating systems sized to cope with current levels of heat loss if
those levels can be reduced by a half or more. In addition, airtight buildings
are more predictable in terms of environmental control and the capital cost
savings of installing smaller heating plant may be augmented by reduced plant room
sizes in certain cases and particularly by reduced running costs in the longer
term. As well as reducing the need for heating plant, airtight buildings offer
much greater potential to respond positively to the local external climate
through passive, or climate responsive design strategies such as natural
ventilation, day lighting, the use of thermal mass and passive solar gain.
Energy savings, capital and running costs, along with CO2 emissions
can thus be further reduced.
Comfort and Control
As noted above, airtight buildings are not as
affected by variations in external conditions. This makes them easier to
control from an Engineer or Designer’s point of view, but it also makes them
more comfortable from the point of view of the occupant.
In buildings with high levels of infiltration those
occupants near draughty windows, for example, will suffer the cold,
particularly on windy days, whereas those elsewhere may well suffer from too
much heat locally as the system tries to raise the temperature overall. Those
who try to achieve comfortable levels through the use of the provided
ventilation controls will find these to be relatively ineffective, whereas in
more airtight buildings greater levels of control and comfort generally are
achievable and local control and variation by occupants can have a more direct
effect. In one example of an existing superstore, the ambient temperature in
the store was raised by 5oC after the store had been sealed. Complaints
by occupants in leaky buildings are common, and remedial measures are usually
difficult and expensive.
Deterioration of Fabric
Leaky buildings allow cold air in through the
construction causing discomfort, they also allow warm (and often moist) air
out, causing heat loss. This warm and often moist air can find itself in colder
parts of the outer construction where it can cool, and the moisture in the air
can condense, leading to a buildup of moisture. This in turn can lead to:
• decay of organic
materials such as timber frames
• saturation of
insulating materials thus reducing their insulative effect (which increases
heat loss further)
• corrosion of
metal components
• frost damage
where moisture has accumulated on the cold side of the insulation.
6.3 Legislation
In England
and Wales the relevant regulation on air tightness is contained within Approved
Document L1 for dwellings and L2 for non-domestic buildings (2006). There is
general encouragement to consider air tightness issues, with a target air
permeability for all buildings of 10 m3/hr/m2 envelope area at 50 Pa. In L2, buildings with a floor area
of greater than 500 m2 are required to be tested if approved details are not
used. Further tightening of the regulations are due in 2010.
Proposals
for changes to the Energy standards were issued to public consultation in March
2006, including guidance that air tightness testing would be required if the
calculation of energy performance included air permeability rates lower than
10m3/m2h at 50 Pa.
6.4 Measurement
A range of
units for measuring air tightness/air leakage have been used in the past and
this can complicate matters. However, one method only – “air permeability” - is
the measure used in European Standards, the new editions of the various UK
Building regulations and in CIBSE’s TM23 Testing methodology and has been used
throughout this document. The Air Permeability is defined as the volume flow in
cubic metres of air per hour per square metre of the total building surface
area (including the floor) at 50 Pascals pressure differential, expressed in m3/hr/m2 @ 50 Pa.
The main
difference between the air permeability and previous practice in the UK is the
inclusion of the non-exposed ground floor in the calculation of the ‘total
surface area’ of the building. The difference between the new measurements and
older ones tend only to be marked therefore where there are large volumes and
ground floor areas.
Of the
range of measurements used previously, the “Average Air Leakage Rate (or
Index)” is similar to the “Air Permeability” except that non-exposed floors are
excluded from the measurement. Another common expression is the “Air Changes
per Hour at 50 Pascals (ACH @ 50 Pa). This is a useful measurement in
particular because, when divided by twenty, it gives an approximate value of
the natural infiltration rate of the building at normal atmospheric pressure,
which can then be used to help size heating and ventilating plant etc.
Yet
another measurement is the “Equivalent Leakage Area” (ELA) at 50, 10 and/or 4
Pascals. This figure gives a representation of the sum of all of the individual
cracks, gaps and openings as a single orifice and helps to visualise the scale
of the leakage problem. The main problem of changing the measurement technique
is the ability to compare data
The
standard pressure differential used is 50 Pascals. This is not in fact a very
large pressure differential and corresponds to the pressure exerted by a column
of water 5mm high. Compared to the fact that buildings can withstand wind
induced pressures of at least 500 Pascals, this seems insignificant, but it is
larger than wind induced pressure on a calm day, and by testing and quoting air
leakage figures at 50 Pascals, inaccuracies are reduced and repeatability is
improved.
6.5 Targets
As noted
above, the only ‘official’ guidance in the UK applies in England and Wales and
relates to non-domestic buildings over 500 sq.m in area. As can be seen from
the table below, the target of 10 m3/hr/m2 at 50 Pa. is relatively easily achieved compared to the good
and best practice noted in the 2000 document by CIBSE, TM23. This sets out the
air tightness/air leakage testing methodology which is the de-facto methodology
now followed in the UK.
A number
of air tightness experts believe the stated targets are inadequate when
compared with the overwhelming need to address carbon emission reductions, and
the potential to do so through air tightness measures. For example, the house
illustrated to the right was built in 1992 for the same cost as nearby houses
and improved upon the standards noted above by two thirds.
Building Type Air Permeability (m3/hr/m2 at 50 Pa)
Good Practice/ Best Practice
Dwellings 10.0/ 5.0
Dwellings (with balanced mech.
vent.) 5.0/ 3.0
Offices (naturally ventilated)
7.0/ 3.5
Offices (with balanced mech.
vent.) 3.5/ 2.0
Superstores 3.0/ 1.5
Offices (low energy) 3.5/ 2.0
Industrial 10.0/ 2.0
Museum and Archival Storage 1.7/ 1.25
Cold Storage 0.8/ 0.4
7.0 Designing for Airtightness
7.1 Key Principles
1. A Performance
Specification is a crucial document for establishing the appropriate targets
for airtightness, along with the methodology for achieving it, and the roles
and responsibilities of those involved.
2. Conceiving of
a building in zones and air barriers will help all involved to visualise the
task.
3. Air barriers
must be impermeable, continuous, durable and accessible. They should be
supported by positive mechanical seals where possible.
4. The simplest
solutions will be the most buildable and durable.
5. A culture of
airtight construction does not yet prevail and until it does, it may be
necessary to follow up targets with specific details and specifications, along
with guidance on the process of implementing the necessary level of co-ordination
and attention to detail.
Unlike
design for deconstruction (the subject of the first in this series of SEDA
Guides) and the forthcoming guide on chemical-free design, the design of
airtight buildings cannot be left to the specification and details, at least,
not until the industry as a whole recognises the need and has sufficiently
widespread experience. For the next few years, it will be necessary not only
to provide careful details and performance specification, but also to develop
thorough inspection and testing regimes, hence the need for Chapters 7.4 and 7.5
of this guide.
7.2 Performance Specification
The
Performance specification may be the only document needed by the Architect /
Designer / Client if the building is to be procured through Design and Build
or similar route. However, it is more likely to be part of a suite of documents
including detailed drawings.
The
performance specification allows appropriate targets to be set for the project,
along with a description of how the process is to be conducted, in terms of
scheduling, audits and testing, and potentially remedial works. Given the
increasing use of specialist subcontractors, particularly in larger projects,
it is also critical that the performance specification sets out both the
responsibility for, and constructive guidance regarding the co-ordination of
trades with respect to the final air permeability of the completed envelope.
Zones and Barriers
Once
appropriate targets have been set for the project, the next task is to identify
zones which require greater or lesser airtightness levels. Ideally, these
zones need to be identified on a drawing which also identifies the specific air
barriers in red.
For
example an industrial unit with office space is divided into five separate
zones, and air barriers are identified as required. Such a drawing, however
diagrammatic initially, helps to conceive of the subsequent specification and
detailing needs, giving an overview of the problem.
Heated
zones need to be kept separate from unheated zones such as roof voids, delivery
bays etc. whilst service shafts may require particular attention. Boiler rooms
with large flues and intake vents may need to be separated.
Entrances
are often significant sources of draughts. Lobbies with doors set apart by
around 4m, so that one door closes before the second is opened, can be
effective, whereas in highly trafficked areas revolving doors are likely to be
preferable. Tall buildings, with atria, stairways and service shafts all of
which rise through the building can be prone to ‘stack effect’ air movement
whereby warm air rises, dragging in cooler air from outside at the lower levels
creating more acute air leakage problems. A number of tactics may be employed
to reduce the effects, but in any event issues of airtightness are likely to be
highlighted in these cases.
7.3 Design
With the zones and air barriers located, it is
necessary to design the air barriers themselves.
To be effective, the air barrier must:
• be made of
suitably air impermeable materials;
• be continuous
around the envelope or zone
• have
sufficient strength to withstand any pressures created by wind, stack effect or
air control systems
• be easily
installed
• be durable
• be accessible
for maintenance / replacement if appropriate
The last of these is important since there is
evidence that the airtightness of some constructions will tend to decrease
over time and in particular the first period after completion.
There are a number of strategic measures which can
be employed to simplify the business of designing an airtight building. Since
service penetrations in and out of a building provide a major source of air
leaks, one strategy is to collect all such penetrations into one accessible
area.
In construction types such as steel and timber
frame, it is usually wise to employ a specific membrane or layer as the air
barrier, rather than rely on sealant between, for example, the sheathing
boards. Such a membrane can usually double up as the vapour barrier if used
internally and gives the Designer the opportunity to consider and address
airtightness explicitly, rather than as a function of other elements. Bear in
mind that most membranes are flimsy and will need support in all areas.
Another strategy is to employ service voids.
Creating a service void internally allows for alteration and maintenance of
services and finishes without recourse to penetrations through the air
barrier. This allows for long term good performance in contrast to membranes
which are liable to penetration at all service points, necessitating careful
sealing of each and every penetration, not only initially, but over the years
of alterations and maintenance to come.
Generally,
it is better to conceive of the joints in airtight layers as ‘positively’
connected, anticipating differential movement and decay of adhesive or
chemical bonds. For example, where different components of a curtain walling
system are liable to differential movement, it is clear that a joint whereby
the two components are held together with a positive mechanical connection
across a compressed gasket is likely to remain airtight longer that a simple
butt joint with a mastic sealant between.
Finally it is clear that complex solutions to
airtightness are likely to be more prone to poor execution and potentially to
greater vulnerability to differential movement, failure of sealants,
dislocation of components and so on. It is important therefore to aim for the
simplest solutions to providing a robust airtight layer, using the fewest
separate materials, junctions and penetrations, and the easiest installation
and maintenance.
It is
worth making a point of considering each and every specified component with
regard not only to its own intrinsic airtightness characteristics, but with
regard to the connections between it and adjacent components. It is important
to provide explicit details and guidance at specific, and particularly tricky
detail areas. On design and build contracts it may be necessary to allow for
some form of review of proposed solutions and procedures.
The following provide a few examples whereby
airtightness can be simplified at the earliest design stages.
However good the workmanship, blockwork on its own
can never be considered airtight. Once plastered, on the other hand, it may be
considered extremely airtight, with concern only for those edges and corners
where cracking or gaps can appear. This may be contrasted with the more common
practice of drylining block walls with plasterboard on battens or dabs.
Design & Detailing for
Airtightness
Services
Zones or Rooms enable a range of services to be collected together before
exiting the building, allowing most of the penetrations in the external fabric
to be grouped and sealed effectively.
Service
voids enable cables and pipework to be installed and altered without needing
to penetrate the air barrier. Note however that if they are not run in conduit,
protection may be needed against subsequent fixings. Source: C. Morgan
Positive physical connections are
to be preferred over any other joint such as one relying on adhesives. In the
timber frame example shown the air barrier membrane is shown lapped and sealed
with mastic over a firm background (boards with stud behind) and with a
positive mechanical fix - a batten - fixed over the top and through to the
stud.
Trinsically non-airtight block wall behind, this
form of construction typically gives rise to a wide range of air leakage paths
behind the boards and into floor, partition wall and ceiling cavities. From the
perspective of airtightness, drylining should be avoided unless great care is
taken. See right.
Similarly, timber floors are difficult to seal well
without a good deal of care. On the continent - and to an increasing extent in
the UK at large - concrete floor systems are being used for both ground and
first floors (often for other reasons such as acoustics, fire and the desire
for underfloor heating) and these are easier to make adequately airtight.
Hollow planks however can leak into cavities and require to be sealed at their
ends, this will dramatically improve air tightness
One
important and often quoted example is the timber first floor connection with a
block wall inner leaf. Who is responsible for ensuring absolute airtightness
when the timber joists rest on the wall and are infilled between with block and
mortar? Presumably the bricklayer, but is it then his fault if the timber is
installed at the wrong moisture level and subsequently twists and warps,
leaving cracks around every joint? Is it really feasible to attempt to tape or
mastic seal around them all, and what if the underside of the ceiling is to be
exposed? Far better perhaps, to do away with the joist-onto-wall detail altogether
and replace with joist hangers. Increasingly, the designer should be seeking
solutions which are intrinsically airtight because of the design, rather than
continuing as before while accepting an increased use of duck tape and mastic
on site! Whilst these may get you through the initial airtightness tests/air
leakage tests, they are short term solutions and not likely to lead to the
anticipated energy savings for the Client in the long term.
A good
review of the various materials and components which allow the Designer to
create an air barrier may be found in the BRE Report BR448: Airtightness in
Commercial and Public Buildings
7.4 Detailed Specification
Beyond the
performance specification illustrated earlier, it is important that the issue
of air tightness/air tightness testing becomes embedded within the standard specification
vocabulary.
Where an
equal or approved alternative may be allowed, it is critical that an
airtightness performance specification is part and parcel of that equality of
performance. For example, it may no longer remain satisfactory merely to
specify a membrane, but in addition to specify the fairly precise nature of the
sealing, overlapping and potentially the subsequent layers as well. Simply offering
a performance specification and ensuring the responsibility resides with the
Contractor is all very well, but it is important too to offer solutions that
will enable a satisfactory outcome to be achieved.
Design & Detailing for
Airtightness - Implementing Airtightness
In
addition to the intrinsic lack of airtightness, a problem of drylining is that
it can create hidden pathways for air, as above, into the void above suspended
ceilings and elsewhere throughout the building
Timber
joists built into a block wall - a poor detail for airtightness. Far better to
use joist hangars and avoid the problem. Source. Concrete planks are not free
of problems eitherhollow planks are often left ungrouted where they meet the
external wall, which could lead to extensive air leakage internally.
7.5 Implementing Airtightness
Key Principles
1.
The Contractor or Project Manager must be made
responsible for achieving the air tightness levels set. In particular, this
will involve careful co-ordination between trades; if this doesn’t happen then
an air leakage/air tightness failure will surely follow
2.
Inspection remains an integral part of achieving
air tightness and passing the air leakage test.
3.
Ideally at least 2 air leakage tests (air tightness
tests) will be undertaken; the first when the building is weather tight, and
the second air tightness test a couple of weeks or so before handover.
4.
Experience suggest that making one person (or team)
responsible for air tightness is the most effective way to tackle the issue.
5. Remedial air tightness works to existing
properties can reap substantial benefits without undue disruption.
It is not
yet generally possible within the UK to specify that a building shall be
airtight and leave it to the Architect or Contractor to sort out. There is not
yet a culture of airtight construction, except perhaps, amongst those who
construct superstores.
The
responsibility of the Designer in regards to the airtightness cannot be
overestimated, for if airtight buildings are to become main stream, as they are
elsewhere in the world, the techniques must be above all simple and buildable,
with most if not all of the ‘tricky’ areas designed out from the start. In this
way, such techniques can become ‘second nature’ to Contractors and there is
less reliance on potentially adversarial inspection and air leakage/air
tightness testing failures.
Ideally
too, the Designer will understand the issues sufficient to prepare a sound
performance specification – giving achievable targets for airtightness as well
as a clear description of responsibilities and procedures, and a clear and
practical set of overall and detail drawings, along with a detailed
specification.
In the
meantime, and even with good documents, there is likely to be a need for effort
and vigilance by both the Design Team and the Main Contractor or Project
Manager on site. This chapter briefly describes this effort, while the next
describes in more detail the actual air tightness testing procedures and
auditing techniques used.
7.5 Plan of Work
The RIBA
Plan of Work provides a framework for the entire design and construction
process. The table on the next page allocates specific tasks relating to
airtightness to each Work Stage to enable a schedule of tasks and
responsibilities for the Design team to be prepared according to each project.
7.6 Roles and Responsibilities on Site
Designer /
Design Team
The
responsibilities of the Design Team are detailed on the following page,
showing all stages including site works and beyond. Buildings usually comprise a number of different components,
creating a myriad of routes through which air can escape if not carefully
sealed at each and every junction. The Designer’s role is to simplify these
details to reduce difficulties on site.
It is
critical that the purpose of pursuing air tightness is explained so that all
concerned understand why they are being asked to attend to these issues. The initial
briefing of key personnel at mobilisation stage – whether or not this involves
the air tightness specialist – is also critical in determining the approach to
conducting the works, inspection, air tightness testing and auditing etc.
which will need to be dovetailed into the many other concerns on site.
On large
projects it may be useful for one member of the Design Team to take special
responsibility for air tightness / air leakage testing issues.
Contractor
The Main
Contractor’s principal responsibility is to deliver the air tightness
performance overall and the most likely task on any but the smallest jobs will
be that of co-ordination between the subcontractors. The Main Contractor must
be clear that he carries responsibility for the overall air tightness and in
turn must ensure that all subcontractors are clear about the extent of their
responsibilities. This is important since there may be some deviation to
conventional practice in order for air tightness to be achieved. It is always
prudent to place someone in the site team who has experience of air leakage/air
tightness on their previous projects as their experience may avert a potential air leakage/air
tightness failure
RIBA
Work Stage Design Team Tasks
A Appraisal Establish appropriate air
permeability rate
B Feasibility / Briefing Note
Microclimate
Test
existing buildings / building to be refurbished
Identify
procedure for review and testing
C Outline proposals Consider a/t issues
in relation to decisions about form of construction
Identify
zones and layers
D Detailed Proposals Identify
requirement of additional consultants / design by specialists
E Final Proposals Ensure co-ordination
between DT to ensure a/t envelope & penetrations
Detailed
application of airtight materials, junctions, service penetrations
F Production Info Select sub-contractors
for specialist works (incl. testing)
Careful
specification of components, membranes, materials
Emphasise
methods for airtightness on documentation
Careful
specification of components, membranes, materials
Emphasise
responsibilities in specification for dealing with ‘loose ends’ between
sub-contractor interfaces
G Tender Docum’n Define Contractors’
responsibilities for co-ordinating work sequences
H Tender Action Ensure selected tenders
include adequate airtightness procedures
J Mobilisation Brief all involved in
areas critical to air infiltration before work starts
Preparation
of samples, training, testing and QA procedures
K-L Site Works Co-ordinate inspection with
Building Control if required
Ensure
inspection of areas to be covered
Ensure
audits and testing schedule is adhered to
Ensure
design changes do not compromise airtightness performance
M Post Completion Obtain feedback from
concerning comfort and energy consumption
Carry
out remedial work as required at end of DLP.
As with
the Design Team, experience suggests that the best performance has been
achieved by Contractors who employ a dedicated individual (or team) to carry
responsibility for airtightness/air leakage, to inspect the works and instruct
as required.
For
Contractors, the issues of airtightness/air leakage are intimately linked to
issues of good or bad workmanship in general and this can make the issue both
more sensitive, but also more difficult to control. Even simple buildings are
immensely complex and so the most important aspect of all is the creation of an
overall culture of careful, tidy, accurate and airtight construction,
something which cannot be simply forced through with a performance
specification.
It is easier
to specify and draw an airtight detail than to build it, and so the emphasis on
inspection and Contractor responsibility has not developed from a prejudice
against Contractors, but from a realistic appreciation that this issue cannot
be entirely resolved ‘on paper.’ It is genuinely about a culture shift (at
least for many in the industry) and this is where the real challenge lies. Once
this shift is adopted there will be a far higher percentage of companies
passing their air leakage/air tightness testing at the first attempt
7.7 Inspection
Air
leakage found in dwellings according to studies undertaken by BRE. The studies
offer a range of conclusions, the most significant of which is that the
greatest volume of air leakage is occurring in areas out with the ‘normal’
consideration of ventilation, through the myriad of cracks and openings all
over the building which is described as ‘background air leakage.’
Of the
background air leakage subsequently investigated, the principal air leakage
routes were noted as being:
• Plasterboard dry lining on dabs or battens, often linked to
routes behind skirtings etc.
• Cracks and joints in the main structure; open perpends,
shrinkage & settlement cracks
• Joists penetrating external walls, esp. inner leaf of
cavity walls
• Timber floors, under skirtings and between boards
• Internal stud walls, at junctions with timber floors and
ceilings
• Service entries and ducts
• Areas of unplastered masonry walls; intermediate floors, behind
baths, inside service ducts
.
It is
perhaps worth mentioning that the BRE results were based on buildings using dry
lining on masonry walls and timber floors. Had the masonry walls been
plastered, if concrete floors had been used, and if basic airtightness measures
were taken, it is likely that the principal problems would occur around service
penetrations, and, to a lesser extent, around windows, doors and rooflights.
This is the experience of countries where envelope airtightness generally is
more developed. As a result they achive far better first time air leakage/air
tightness results
The following table lists many of the most common
infiltration problem areas. On larger projects, common problems include:
·
Incomplete
bulkheads at eaves;
·
Gaps where
block work abuts to steel columns or beams
·
Uncapped
cavity walls, at eaves (right) and mid-points where cavity walls change to
composite panels
·
Gaps along
the underside of corrugated roof linings
·
Gaps
between block work and steel, and uncapped cavity wall at join with composite
panels Common Locations for Inspection
(Applicable to all types of Construction)
Foundation
/ Ground Floor
·
Check wall
and floor dpcs form an adequate air tightness layer, is a separate layer
needed?
·
Check gaps
at perimeter insulation strips
·
Check
potential movement gaps between loadbearing structure such as columns and
adjacent non- loadbearing slab
First
and Intermediate Floor Levels
·
Concrete
floors: Check joint between the floor and plasterboard to walls
·
Check gaps
between concrete planks, or beam & blocks are sealed at the wall
·
Check
voids under floor finishes and service run penetrations
·
Timber
floors: Check a membrane seal has been incorporated if required
·
Check any
membrane used is supported between joists
Eaves
and Verge
·
Check
continuity of airtight layer between wall and roof / ceiling
Ceiling
level beneath the roof
·
Check for
separation between deliberate roof ventilation and the conditioned zone
·
Check for
service penetrations and hatches which pass across the airtight layer
Boundaries
between different wall envelope systems
·
Check all
systems have a dedicated airtightness layer assigned, and that these can be
constructed to be continuous across dissimilar elements
Windows
and Doors
·
Check that
the frame to wall junction is properly sealed and continuous with the wall
airtight layer, particularly at cills
·
Check the
windows and doors have appropriate weather seals between the opening unit and
the frame
Services
penetrations
·
Check for
proper seals at service entry points, and at points of entry into conditioned
zones. These may also require fire protection
Main
Entrances
·
Check that
the whole entrance area is separated from the conditioned zone by an inner
airtight layer
Lift
Shafts, Service Cores, Delivery Areas / Car Park
·
Check
these have been separated from conditioned zones with air barriers and
draughtproofed access doors
Where profile fillers are used poor workmanship is common
• Perforated (acoustic) roofs, where the unsealed mineral
fibre acoustic layer bridges the eaves of the building, constituting a major
leakage point
• Gaps where plasterboard or wall linings are incomplete, commonly
above suspended ceilings and to the underside of beams
• Incomplete door and window reveals
• Services Penetrations into the building, and between zones
inside the building
Another
common issue is porous blockwork, particularly when internal walls are drylined
rather than plastered or painted. Where this is likely to be unavoidable, it
may be worth requiring blockwork to be tested for air permeability(air
leakage), and to have an AP value (by an accredited lab) that is no more than
50% of the target Air Permeability for the overall building.
7.8 Testing and Audit Schedule
In many
cases to date, an air leakage test/air tightness test has been carried out a
week or so before practical completion. If the result is poor – a high rate of
air leakage – then a great deal of work suddenly needs to be done, often to
areas which have been covered up and the whole business can be both costly and
time consuming, just at the point where in many contracts there is already
considerable pressure on Contractors.
Far better
therefore to schedule the air leakage test/air tightness test at a time where
remedial works are relatively simple to perform. On the other hand, it is
important that a Air leakage test/air tightness test is undertaken close to handover so that the Client
and Design Team can be sure that the completed building accords with the
performance specification.
Ideally
therefore, two Air leakage tests/air tightness tests at least should be carried out. The
first Air leakage test/air tightness test should be undertaken as soon as a meaningfully air-
and weathertight envelope has been installed. Ideally, all air barriers are still
accessible and any defects can be readily put right. This Air
leakage test/air tightness test plus
the audit techniques which are likely to accompany it, may be used to ensure an
acceptable airtightness performance and give a good indication of where
subsequent works may advantageously targeted.
.
In this
way, the second and final Air leakage test/air tightness test serves simply to confirm the performance of the
building, hopefully at a slightly improved level from the first Air
leakage test/air tightness test
without the need for costly and complex operations late in the day.
Such a air
tightness/air leakage test schedule is nonetheless costly in itself, but for
those who have been involved in such testing schedules, experience suggests
that this remains the most cost effective way to deal with the issue. Certainly
it is worth avoiding excessive remedial works at the eleventh hour. With a
sufficiently good first Air leakage test/air tightness test performance, it may even be possible to dispense
with the final air tightness test, if this is deemed acceptable to the Design
Team Leader or Client.
It is
often the case that the envelope is not sufficiently complete on the due date
for air leakage/air tightness testing. This then necessitates a complex process
of temporary sealing of the incomplete areas. It is harder than to ascertain
the location of the air leakage and allowances are made which may prove
misleading. Experience suggests that this is not ideal and it would be better
to put off the air leakage test/air tightness test for a week and carry it out
when the envelope is complete and ‘as intended’.
On larger
projects, more air leakage/air tightness tests may be needed, or more specific
tests of individual areas required. Large projects with multiple units of a
similar nature may benefit from either pre-installation component testing, or
insitu testing of one installed component to establish acceptable airtightness
levels early on.
7.9 Remedial Airtightness Works
With
airtightness testing and a general awareness of airtightness issues developing
around new build situations, the principal area of concern, as with energy
efficiency in general is the existing building stock. In terms of airtightness,
the UK building stock is considerably worse than comparable northern latitude
countries and there
is a good deal of room for improvement, if these improvements do not occur then
a large percentage of companies will fail their air tightness/air leakage
tests.
Either as
a standalone measure or as part of a package of energy efficiency measures
generally, there is scope for remedial works to most of the existing UK
building stock. Relatively simple measures may in many cases be sufficient,
using a wide range of sealants to control air leakage. However, it is important
that such measures are combined with attention to the ventilation requirements
of buildings where, to date, insufficient ventilation has been ‘augmented’ by
infiltration and exfiltration which, if reduced, could lead to other problems.
As with
thermal insulation, there is an extent to which controlling some of the air
leakage merely diverts the flow of air, inward or outward, to another defect or
gap, but there is such scope for improvement that even fairly basic efforts are
likely to reap substantial environmental, financial and comfort benefits for
owners and occupiers alike.
There are
many examples of remedial works described in the various publications noted in
the references. Some of the more successful measures included carefully sealed
secondary glazing installed where old windows had to be kept for conservation
purposes, draughtproofing of doors and entranceways generally, and installation
of lobbies in well trafficked reception areas, attention to draughtproofing of
existing windows and targeted use of flexible sealants to ill fitting
components and joints between different construction types, will drastically
improve your air leakage rate and will should enable you to pass your air tightness test first
time
8. Testing Airtightness
Key Principles
1.
Testing procedure is set out in CIBSE TM 23 and in
BS EN 13829: 2001.
2.
A pressure test/ air tightness test involves sealing all
‘normal’ gaps such as vents and pressurising or depressurising the building. The
level of fanpower required to maintain the pressure differential indicates the
‘leakiness’ or ‘permeability’ of the building.
3.
Pressure tests/ air tightness tests are typically
followed by an audit (using smoke pencils, for example) to expose and make visible
the various air leakage routes.
4.
Where projects comprise large quantities of a
single component, component testing in the laboratory may be appropriate as
well as on site element testing.
8.1 Climatic conditions
As
mentioned in Chapter 1, the raised pressure differential of 50 Pascals created
during an airtightness test/air leakage test is quite small. Whilst this is
adequate to overcome most of the common pressure differential anomalies, such
a small differential is vulnerable to larger pressure differences created by
climatic conditions.
Air
leakage tests/ air tightness tests require calm days – i.e. a reading on the
Beaufort Scale of 3 or less (3.4 to 5.4 metres per second wind speed at 10 m
above ground) This corresponds to a gentle breeze with leaves and small twigs
in constant motion. In winter conditions and on exposed sites therefore testing
may not be possible, although it is often possible to make allowances, so long
as these are carefully recorded.
8.2
The Test itself
Essentially
the process is one of pressurising the inside of the whole building, and of
measuring the rate at which air needs to be blown or sucked to maintain that
pressure differential; a building suffering large amounts of air leakage will
equalise readily and require a greater measurable effort to maintain the 50
Pascal differential, while a air tight building will easily contain the
enforced differential and require little additional input, this will be easily
recognisable within the first couple of minutes during the air leakage test /
air tightness test
The
pressure difference is induced by one or more calibrated fans that are normally
mounted within a suitable doorway. An adjustable door panel system, sealed
around the edges is used which can also be connected to large external fans via
collapsible ductwork if required. The rate of the fan, or the volume flow of
air through the fan can be understood as the rate of air entering / escaping
throughout the remainder of the building envelope.
Buildings
are tested in such a way as to recreate ‘normal’ conditions. Doors and windows
are closed, trickle ventilators closed, extract fans and such like are closed
but not sealed. Internal doors are wedged open.
If the
building is under construction, air tightness testing/air leakage testing is
ideally undertaken out with working hours, but sometimes this is not practical
so some scheduling of work needs to be thought through in advance. With all
external doors and windows sealed shut, some work becomes impossible (such as
work with solvents requiring ventilation) and internal trades are normally
‘sealed in’ for a short time, where they can carry on undisturbed during air
tightness test.
In
existing buildings, air tightness tests are normally carried out when the
building is unoccupied if possible because of the disruption.
8.3 Air Leakage Audits
The air
leakage test/air tightness test quantifies the rate of air leakage through the
envelope as a whole, but it cannot locate the air leakage paths. Where remedial
work is required therefore, air tightness tests are followed by a range of
auditing techniques designed to identify the specific places where air is leaking.
In many
cases a simple visual inspection may be sufficient – especially if undertaken
by someone with experience of the likely locations of leakage, this is a good
way of lowering the risk of a air leakage test / air tightness test failure
However,
most leakage routes are difficult or impossible to spot without visual aids.
One common technique is to use smoke tracers – smoke pencils or smoke
machines. These render the air leakage paths visible in certain situations. The
building may be positively pressurised and the air leaks witnessed externally,
or, more usually, negatively pressurised while a smoke pencil is drawn over
likely gaps and defects which become visible as the smoke is sucked inwards.
Another
technique, which has certain advantages and disadvantages compared to smoke
tracing, is the use of an infrared camera by undertaking a thermographic
survey, Used either externally or internally, these thermographic cameras
register the radiant heat levels of surfaces and so are able to ‘see’ for
example, where cold air is cooling the fabric around a gap internally, or
conversely where warm air is escaping and heating the colder materials on the
external face.
To work
effectively, there needs to be a recognisable difference between the internal
and external ambient temperature, so before any heating has been installed and
on a warm summer’s day thermography / thermographic surveys may not be
effective. Similarly on warm and sunny days, sunshine on external surfaces can
distort the true situation so it is better on such days to wait until early
evening. Conversely, rain on external surfaces can be equally distorting of the
true thermal situation. However, these cameras are useful in identifying
problems at high level or difficult to reach areas, and are also very helpful
in identifying other construction defects such as poorly installed (or
non-existent!) insulation within the fabric.
On larger
commercial buildings, air tightness testing / air leakage testing may be undertaken
at the same time as ‘standard’ ventilation system commissioning and associated
studies
8.4
Component Testing
A distinct aspect of overall air tightness testing
is the individual component test. This may be undertaken quite separately, in
the laboratory or by the manufacturer of a particular component. Such tests may
be deemed necessary on a large project where large areas of one particular type
of component, for example curtain walling, are to be specified.
Insitu element testing involves isolating the area
within a temporary sealed compartment, which is then pressurised, and the air
leakage related to the area of interest assessed. In this way sample areas of a
building may be pressure tested using smaller fans as required.
9. The Details
Caveat
It is important to emphasise the scope and purpose
of the following drawings and specifications.
They are included solely to show practitioners the
sort of alterations that can be made in order to enable buildings to be much
more airtight in general.
Their purpose is not to offer approved details in
any sense, but to illustrate the difference
between details and specifications which do not address
airtightness issues, and those that do. It is the differences between the originals and
alternatives which is intended to be illustrative, not necessarily the
alternatives themselves.
The original details have been taken from
conventional details and specifications we believe to be broadly representative
of their construction types. We hope the principles shown, and the specific
references made will assist designers in making similar changes in their own
work, but it goes without saying that air pressure testing cannot take
responsibility for any work undertaken as a result of the use of these details.
Specifically, these details are not intended to
show best practice in any sense, nor are they even intended to be up to date.
We have striven in the preparation of these details and specifications to keep
as close to the original as possible. We have done this in order to show that some
quite fundamental alterations – in terms of airtightness - may be made with the
minimum of visual or functional impact on the original. Where these original
details and specifications do not meet current standards or aspirations, the
alternatives given are likely to be similarly wanting. To re-iterate, the
purpose is not to produce approved details, but to illustrate the process of
improvement – in terms of airtightness only – that may be made.
Consideration of priorities in airtightness design
and specification is potentially misleading since, in effect, all gaps, cracks
or tears let in air and the sealing of one simply redirects infiltration to
somewhere else. Like thermal insulation, what is important is the level of
continuity generally, not any particular detail on its own. Nonetheless some
prioritisation has been attempted in order to help Designers to prioritise
their own efforts since not all measures may be necessary.
9.1
Steel Frame + Concrete Block Cavity Wall
Original
Specification
Discussion
Because of the largely wet trades involved, one
might imagine a masonry construction is inherently more airtight than the dry fixed
timber frame and curtain walling construction types. However, insofar as
concrete inevitably shrinks as it dries, as mortar beds and perpends are often
poorly filled, and due to the differential movement between masonry and the
steel frame, the myriad pathways that open up can make masonry buildings extremely
susceptible to infiltration.
To make things worse, construction such as this
does not easily lend itself to a simple, single airtight layer which can be
applied separately and therefore the need for vigilance, and some care and
attention to a number of small but potentially time consuming sealing jobs is
high.
It would be possible to form an airtight layer
internally through the use of an applied membrane and the adoption of a
service void. This would have the advantage of allowing for changes in the service
or fit-out provision without the risk of damage of compromise of the airtight
membrane, and for those inclined to this solution.
A parge coat and service void could have a similar
effect, but the use of plaster internally is a common and effective technique
for creating an airtight layer and is preferable in this instance as it is
closer to the original detail.
HIGH PRIORITY
·
Wet
Plaster Finish or Wet
plaster coat costs more but provides a better finish overall, as well as
significantly improved airtightness across the masonry leaf. Plaster should be
extended to all wall areas and not left off in areas which will not be seen,
such as suspended ceilings.
·
Membranes
Lapped & Sealed2 lines of tape and a positive mechanical fixing by batten
ensure laps are sealed for the long term
·
Mastic to
Skirtings, Linings etc.
·
Critical
in this detail since the plaster cannot form a continuous layer at these
junctions
·
Sealed
Cavity Closer: Gaps
around openings are common so care is needed here to prevent infiltration
around the frame and into the cavity
·
Vapour
Barrier Seal at Eaves: Important
here since no effective seal is noted on the original which could lead to
excessive airflow at this vulnerable point.
Costs
The most significant cost implication is associated
with the addition of the wet plaster coat to the inner leaf of blockwork. This
results in approximately a 60% increase in cost, although the quality of the
blockwork is not as critical. This item is also significant in that is changes
the ‘look’ of the detail but is probably the highest priority.
Otherwise, most of the costs are associated with
the additional time, effort and care implicated within the specification and
details. Of these, the most significant is the additional labour and materials
required for the joining of the vapour barrier in the roof, and sealing it
around the perimeter. This work almost certainly more than doubles the cost of
the vapour barrier in the original detail, but again, represents a critical
factor in reducing air leakage.
A number of the measures described represent no
more than a re-iteration of good practice, such as the sealing of perpends,
lapping and sealing of membranes, draught stripping of windows and so on. These
may assumed to incur no cost implication, but perhaps one of attention to
details on site.
The mastic sealant to skirtings, cills and the like
would add about 50% to the costs of these items, though these items represent
only a small fraction of the overall costs.
Taping of the insulation boards would depend
largely on the board type, but might realistically attract only a marginal cost
increase, as would the use of compressible foam around the steelwork.
MEDIUM PRIORITY
·
Concrete
Slab Floors:Concrete slabs form an
airtight layer but joints with penetrations such as perimeter blockwork,
insulation or structural columns must be sealed.
·
Cill to
Window Sealing: Double
sealed detail which increases the chance of securing an airtight seal at this
often overlooked junction
·
Compressible
Foam between Steel and Blockwork: Potential solution to the inevitable gap which will
form here, also sealable with mastic oninside face only.
LOW PRIORITY
·
Perpends
Fully Filled: Not critical if a wet
plaster finish is applied internally, but high priority if they are not.
·
T&G
and Taped Insulation:Not
technically part of the airtight layer, but gaps here simply increase the
likelihood of infiltration (air leakage) and are relatively easily sealed.
·
Expanding
Foam to Gap at Eaves: Not
part of the airtight layer but by sealing a large gap in the fabric, this
reduces the wind pressure driven airflow within the cavity thus reducing the risk
of infiltration (air leakage) indirectly.
9.2
Index
a) Perpends
fully filled
A common problem
with blockwork and brickwork buildings is that perpends are not completely
filled and this
leads to air flow (air leakage) through the wall. To an extent this measure is
superceded by
both points (aa) and (d), but it is still worth making the point in order to
draw
attention to
this workmanship issue in general.
b) Blockwork
Maximum Air Permeability by Component Test
An alternative
to wet plastering the blockwork on the inner leaf is to require a component
test of
the blockwork to
satisfy a maximum air permeability of, say, 5m3/hr/m2 or
less. On larger
projects, or
where wet plastering is unlikely to be effective or desirable, this is one
method of
ensuring a reasonable
degree of airtightness from the blockwork leaf. These conditions may also be
used for the outer leaf but is not as important because it is the inner leaf
which is providing the main air barrier.
c) Membrane
Lapped and Sealed
Typically
membranes are lapped and stapled or tacked, but in order to create airtight
layers, it is
important that
these laps are rigorously sealed. Best practice in this regard - beyond the
correct
use of
Manufacturers’ overlap dimensions, proprietary tapes and other accessories - is
to run a
layer of double
sided tape between the membranes at the overlap and run a tape over the
leading edge of
the outer sheet. In addition, since many tapes tend not to last too well, it is
advisable to
ensure that laps are made directly over supported areas (i.e. with studs or
dwangs
directly behind)
and are held down positively with battens fixed through forming a mechanically
tight, as well
as an adhesive seal, this will provide an especially strong air tightness seal
d) T&G or
Shiplap and Taped Non-Mineral Fibre Insulation
Mineral fibre is
permeable to air movement and cannot be counted upon to help in reducing air
leakage.
Extruded polystyrene and other closed cell plastic insulation materials do not
suffer from
this and so have
the potential to reduce air leakage amd improve air tightness in and out of the
building.
However, they are only likely to do so if they are effectively joined at their
edges, at
corners,
openings and around wall ties etc. For this reason, it is likely that t&g
or shiplap edge
boards (which
are available from a number of Manufacturers) will offer better connections,
and
these can be
further augmented by the use of a sealant tape externally.
e) Wet Plaster
Finish Internally
An alternative
to arranging component tests for the blockwork. A simple block finish with 2
coats
of paint which
in terms of airtightness is an improvement on a uncoated block wall but is not
sufficient to
consider the blockwork airtight in the least. Wet plastering of the blockwork
is more
expensive but
ensures an airtight masonry leaf. The plaster should extend to all areas of the
wall,
regardless of
whether they will be hidden by suspended ceilings or raised floors. It should
extend
right to the
floor and to undersides of steel beams etc. and where broken by service boxes
etc.
should be conscientiously
filled and sealed.
An alternative
which would have a similar effect would be to use a parge coat over the
blockwork,
before
application of a service void and separate finish layer. The simple wet plaster
finish is
closer to the
original.
f) Mastic Both
Edges to Skirtings, Reveal Linings etc.
Where the corner
junction behind has been carefully sealed then this measure may not be
required, but in
the examples shown on this construction, this particular detail is critical
since it
forms an
integral part of the airtight layer, particularly where the plaster has to be
discontinuous.
g) Concrete Slab
Floors
Unchanged from the original
detail, this is simply to note that concrete slabs form an airtight
barrier and may therefore
be considered good practice in this regard. However, no note is made
of the need for care to be
taken where the slab meets elements of structure which pass through,
steel columns, for example.
At these junctions, a compressible foam strip may be laid around the
steel prior to pouring the
concrete if practicable, or a mastic sealant may be used subsequent to
the pour to seal the
inevitable shrinkage cracks which will form and become air leakage paths
h) Insulated and
Robust Cavity Closer
A robust and
insulated cavity closer enables the cavity to be effectively closed, the gap to
be
bridged with
insulation without risk of moisture flow between inner and outer and the window
to
be securely
fixed at the head and jambs if required. The gap between window frames and the
main wall is a
notorious place for infiltration (air leakage) so it is important that this
junction is
carefully
sealed. The flanges of the cavity barrier should be closed against the
blockwork faces
with a
continuous mastic bead between on each flange so that airflow into the cavity
from outside
or in is
prevented, thus resulting in better air tightness
i) Proprietary
Cill with Foam Sealant Internally and Mastic Sealant Externally
In addition to
the mechanical fixing of the window frame through the cill piece, it is
important that
this fixing is
made through a compressible foam strip which is then sealed against air leakage
from outside
with a mastic type sealant. This gives the Contractors two opportunities to
ensure a
completely
airtight seal at this particularly vulnerable point.
k) Compressible
Foam Strip beneath Steel Beam to Blockwork Top
For reasons of
both initial shrinkage and subsequent structural movement, it is to be expected
that a direct
connection between a steel beam (or column) and a block wall will open up over
time
to form a
potential route for infiltration (air leakage). One way to try and reduce this inevitable
gap
is to build the
blockwork against a compressible foam strip which immediately expands to fill
the
gap between and
remains flexible thus continuing to fill the gap even after shrinkage and
movement. Since
compressible foam strips are not intrinsically airtight, mastic sealant should
be
used in addition
to form a neat internal joint which should further seal the connection, thus
drastically
improving air tightness
l) Vapour
Barrier Detail at Eaves
Here the vapour
barrier is positively sealed to the steel perimeter beam to properly seal the
ceiling vapour -
and air - barrier along its edge. Assuming that the steel beam is without
penetrations (a
specification note has been added to ensure that this is checked) then as long
as
the plaster seal
to the underside of the beam is adequate, an airtight layer has been formed
which may be
discontinuous in materials but continuous in terms of airtightness.
m) Expanding
Foam to Large Gap at Eaves
Whilst not
strictly part of the airtight layer, this measure reduces the potential wind
pressures on
the cavity which
in turn reduces the risk of infiltration through the airtight layer itself.
Note also the
introduction of
a ply layer above to support the insulation (nothing is noted as doing so in the
original detail)
but significantly against which the foam can create a firm seal which should
drastically
improve air tightness
n) Mastic
Sealant to Joints
Additional notes
to seal connections between dissimilar materials which are likely to provide
routeways for
airflow (air leakage) unless conscientiously sealed.
o)
Draughtstripping to Windows and Doors
Most
commercially available joinery, metal or plastic windows and doors will be
adequately
draughtstripped
but it is important to explicitly ensure that this is the case, and that seals
(preferably
tubular rubber / epdm type) are accessible and can be easily replaced should
they
begin to fail to
adequately seal when closed.
9.3
Timber Frame with Concrete Block Outer Leaf
Original
Specification
Discussion
Despite the inherently dry fixed nature of timber
frame construction, it offers good opportunities to ensure airtightness because
of the existing convention of using vapour control layers internal to the
insulation and breather membranes externally. This gives the Designer two
layers with which to work to form a robust airtight envelope overall, and without
introducing any significant or new component.
The outer layer of blockwork (or brick, or dry
cladding of any type) need not perform any major role in the airtightness
strategy.
Although there are a large number of small adjustments
to conventional practice outlined, none of these, except perhaps the addition
of the service void and backing board involve any major shift in construction
process. Experience suggests that such changes are readily made and subsumed
within the standard details and specification clauses of the practice.
More tricky is the need to convey the need for
greater effort, co-ordination, care and vigilance to Contractors for whom there
is little to be gained from the good practice noted, and quite a lot to be lost
in terms of potentially time consuming additional tasks. In the short term it
is important to emphasise the additional co-ordination and tasks to Contractors
at the time of tendering so that these are not overlooked and the extra effort
can be adequately assessed.
HIGH PRIORITY
a)
Continuity of Layer / Co-ordination of Trades
General
measures to ensure tradesmen are aware of the need for air tightness that all
involved are conscientious and rigorous, and that someone is responsible for
co-ordination between trades
b) Service
Void
Use of a
service void means most if not all penetrations through the vapour control and
airtight layer can be avoided.
c) Joist
Hangers
Use of
Joist hangers avoids the common problems of air infiltration where joists are
built into the inner leaf
d)
Membrane to Floor Perimeter Beams
Slightly
awkward solution for solving the problems of discontinuity at this area which
is nearly impossible to solve otherwise.
e)
Flexible Foam around Joinery
Gaps
around openings are common and neat, effective solutions can be difficult,
careful use of flexible foam enables effective and durable seals to be formed.
f)
Continuous Layer Over Partitions
High
priority because of the high potential exfiltration rates and condensation
risks at this point
g) Backing
Boards
Use of
backing boards makes installation of the membrane easy and thus less prone to
poor workmanship and subsequent failure.
MEDIUM PRIORITY
a)
Membranes Lapped & Sealed
2 lines of
tape and a positive mechanical fixing by batten ensure laps are sealed for the
long term
Costs
Not surprisingly, the addition of the service voids
adds considerably to the costs of both the walls and ceilings. Of course, such
costs say nothing of the increased ease of services installation, nor of the
long term benefits of a much greater access for upgrading and alterations.
Nonetheless, the addition of the OSB and battens
forming the service void in the walls adds approximately 35% to the cost of
the external wall. Mechanically fixing the vapour barrier to the floor and
taping would add approximately 4% to the overall wall cost in addition.
Adding the service void to the ceiling would
represent an approximate 130% increase in cost over just the 2 layers of
plasterboard. But again, services installation would be easier.
The additional work associated with the breather
membrane would incur a similar additional cost, but may not be a priority if
the internal vapour barrier is well installed.
The mastic sealing of the skirting boards would
increase the cost of their installation by about 50%, although these represent
only small costs overall, the use of polythene strips at the floor and eaves,
and the use of foam around the windows would attract only a marginal cost
increase.
The use of flexible insulation need not attract any
increase in cost if a common, economical type was chosen.
MEDIUM PRIORITY
a) Joinery
Draughtstripping
Tubular
seals are probably the best option.it is important that they can be easily accessed
for maintenance and replacement.
b)
Continuity at Openings
Continuity
between the framing sealant (m) and the membrane can be tricky and care is
needed to ensure a good, durable seal.
c) Seal
Loft Hatches
Unsealed
loft hatches may contribute to air leakage, so worth some care.
d)
Plasterboard Penetrations
If the
airtight layers are sound then this should not matter, but still worth
attention.
e)
Flexible Not Rigid Insulation
Flexible
Insulation provides a better fill between studs, rafters etc.
LOW PRIORITY
a)
Continuity Behind Lintols
An extra
strip of membrane to form a continuous layer when the main one is lapped over
the cavity barrier, also fill behind lintol.
b) Mastic
to Skirtings, Linings, Cornices
Not
necessary if the airtight layer is sound
c) Air
Barrier to Ceiling
HIgh Priority
in separating floors
d) Laying
Tape to Plasterboard Junctions
e) Wall
Tie Fixings
f) Top
Runner Strip Seal
g)
Airtight Service Boxes
h)
Corrosion Resistant Fixings
9.3 Index
e) Wall Tie Fixings to Timber Frame
The breather membrane is not the main air
barrier, but it is nonetheless a useful ally in reducing air leakage through
the construction generally. Ensure that wall tie fixings do not lead to damage
to the membrane (as this will lead to large amounts of air leakage), ideally, by taping over the area of membrane
at which the tie is fixed.
(b) Use of Corrosion Resistant Staples or
Fixings
Non-corrosion resistant fixings to external
breather membrane can corrode to a point where they fail, allowing the membrane
to come loose, often creating a small hole in the membrane and reducing the
effectiveness of the membrane as an airtight layer, this will allow for air
leakage. Copper is non-corrosive but can affect polyethylene, whereas
stainless steel has no effect on polyethlene and so should be preferred.
(c) Membranes to be Lapped and Sealed
Typically both internal and external
membranes are lapped and stapled or tacked, but in order to create airtight
layers, it is important that these laps are rigorously sealed. Best practice in
this regard - beyond the correct use of Manufacturers’ overlap dimensions,
proprietary tapes and other accessories - is to run a layer of double sided
tape between the membranes at the overlap and run a tape over the leading edge
of the outer sheet. In addition, since many tapes tend not to last too well, it
is advisable to ensure that laps are made directly over supported areas (i.e.
with studs directly behind) and are held down positively with battens fixed
through forming a mechanically tight, as well as an adhesive seal. This
requires consideration of lap positions early on if extra framing or subsequent
battening is needed.
(d) Ensure Continuity of Membrane /
Co-ordination of Trades
Whilst this is easy to achieve across large,
flat areas, it is more difficult at the many awkward angles, junctions, corners
and so on on a typical site. There is no specific guidance except to ensure
that those responsible for installation of the membrane are rigorous and
conscientious in their attention to all of the inevitable nooks and crannies,
and that the person responsible for co-ordination is equally attentive,
particularly when the junctions are between separate forms of joint and
separate trades. Having someone experienced on previous projects that required
air tightness tests is a huge advantage
(e) Ensure Membrane is taken into Opening
Reveals, Taped and Sealed and Made Continuous with Opening Seals
it is typical at openings in timber frame
buildings to allow the membrane to run across the opening initially, then form
a star cut into the opening, folding over the sections of membrane and trimming
as necessary. In these cases, there are inevitable gaps in the airtight layer
at the corners of the opening, and it is important to ensure that these are
made good before subsequent installation of joinery etc.
(f) Fix Airtight Membranes to Firm Backing
Boards
In conventional timber frame construction,
vapour barriers are fixed across studwork, usually after the installation of
insulation and prior to the fixing of the internal lining. Equally external
breather membranes are sometimes installed across gaps between rafters or
studs. In both cases membranes are susceptible to pressures from both sides,
leading to the membrane breaking free of its fixing and creating holes in the
airtight layer. Ideally, membranes should be fixed against a firm backing board
by way of protection against damage of this nature.
(g) Service Void
The principal advantage of a service void is
related to functionality and maintenance over time, but a secondary advantage
which relates directly to airtightness is that since all services may be
incorporated within, that is, on the inside of the vapour control layer, there
is no need to penetrate the layer at each and every service installation, thus
significantly cutting down on the myriad potential gaps that are typically
formed and either left, or made good which is time consuming and costly.
(h) Laying Tape at Plasterboard Junctions
Using laying tape at junctions makes the
formation of an airtight junction both conscious and relatively easy, even
allowing for subsequent shrinkage and cracking of the skim layer.
(i) Airtight Service Boxes
Developed in Canada where airtight
construction is more advanced, these service boxes are fitted with gaskets and
a flange surround allowing for an airtight seal at all openings in the lining.
(j)
Mastic Both Edges to Skirtings, Reveal Linings, Cornices etc.
Where the corner junction behind has been
carefully sealed then this measure may not be required. In addition to the nail
or screw fixing, a mastic seal both edges aids efforts to guard against
infiltration/air leakage, but it makes removal and alterations more difficult.
(k) Ensure Continuity of Membrane behind and
around Lintols
It is likely that to achieve this requires
two separate measures. First the breather membrane needs to be continuous and
extend into the opening, thus a second strip should be affixed to the wall and
lapped and sealed to the main membrane which must lap over the lintol or cavity
barrier etc. Second, it is likely that gaps could form between the top, outer
edge of the joinery and the lower, inner edge of the lintol, leading to a
cavity behind the lintol. This cavity should be filled with expanding foam or
mineral wool and if possible the gap filled, probably with a mastic sealant.
(l) Flexible Foam Sealant around Joinery Insertions
Gaps around openings are one of the most
common of infiltration paths. They range from 0 to 20mm, which is too large to
be filled by mastic. Compressible flexible foams are ideal for this
application. Ensure that the airtight membrane meets the seal on both sides to
maintain the airtight layer overall.
(m) Draughtstripping of Openings in Joinery
Draughtstripping of joinery comes in many
forms. It appears that synthetic rubber or elastomeric tubular seals work well,
creating good seals with minimal compression, depending on the size of the gap.
It is important that seals are unaffected by paintwork and subsequent
decoration, or are easily accessible and removable. This is important so that
seals can be replaced as they start to fail to maintain the airtight layer.
(n) Seal all Penetrations in Plasterboard /
Internal Lining
Even with the use of airtight outlet boxes
there will be inevitable penetrations such as ceiling pendants, pull cords,
recessed fittings etc. which must be made good manually, typically with mastic.
(o) Seal Loft Hatches
Generally, this involves a continuous bead
of mastic to the underside flange, and, depending on the design, the use of
compressed and flexible foam, or mineral fibre etc. above. Please note in our
experience this is a common area for air leakage
(p) Use of Joist Hangars as Opposed to
Built-in Joists
The original specification here is already
good practice, that is, the use of joist hangars which sidestep the problems of
joist movement and shrinkage allowing infiltration and airflow within the floor
voids.
(q) Membrane Strip to Inner Face of Floor
perimeter Beams
100 gauge polythene or similar fixed to the
inner face of the perimeter beams early on in the framing process can lapped
and sealed to the internal vapour control layer typically installed a good deal
later, so that a continuous internal vapour control and airtight layer may be effectively
created.
(r) Continuity of Membrane to Ceiling over
Partition Walls
ideally this would comprise a continuous
membrane affixed before the partitions are installed. However it is more likely
that partitions are installed before, therefore such a layer would require
strips to be fixed to the partition top runners to be later lapped and sealed
to the ceiling vapour control layer.
(s) Flexible, Rather than Rigid Insulation
Rigid insulation between joists, studs or
trusses generally has to be cut to fit and this is never 100% accurate, leading
to myriad gaps and routes for airflow. Flexible insulation avoids this problem.
(t) Top Runner Strip Seal
The use of this strip, lapped and sealed
with subsequent membranes both sides prevents infiltration into the wall itself
from the ventilated eaves area, thus ensuring continuity of the airtight layer.
(t) Air Barrier to Ceilings
In ceilings within dwellings of the same
occupancy, this is unlikely to be useful, but in separating floors, it is
extremely important that an air barrier is included in the floor and ceiling
make-up. Noted here by way of a reminder.
9.4 Steel Frame + Glazed
Façade
Discussion
It is important to be confident that the curtain
walling manufacturer, supplier and installers all share an explicit commitment
to producing an airtight wall overall, as it will be very difficult for the
Main Contractor to ensure a continuous airtight fabric if this element is not
firmly ‘tied down’ before the start on site.
The focus of concern then falls to all the various
corers and perimeters where the system meets other construction elements and
here both Designer and Contractor need to have carefuly considered in detail
each occurrence and made adequate provision, to avoid large amounts of ad hoc
remedial work.
The roof membrane must be carefully sealed and the
perimeter condition considered so that a continuous and positive connection can
be made.
HIGH PRIORITY
(a)
Curtain Walling Performance Spec.
Since this
represents the largest area exposed to wind it is important that the
performance specification is adequate and that the components are
conscientiously installed
(b) Mastic
Perimeter Seals
With the
main curtain walling components installed and airtight, the next most significant
air leakage route is likely to be the perimeter seals. Both mastic and
membrane seals are valuable in this regard.
(c)
Membrane Perimeter Seals
With the
main curtain walling components installed and airtight, the next most significant
air leakage route is likely to be the perimeter seals. Both mastic and
membrane seals are valuable in this regard.
(e) Roof
Membrane Sealing
Any
leakage in the roof membrane or at the roof / wall junction could be serious in
terms of both energy waste and risk of moisture related damage to the roof
build-up, so this detail is important.
MEDIUM PRIORITY
(h) Plates
Added to Beam
Because of
the difficulty in forming an adequate seal to protruding beams, this is likely
to be a major source of air leakage in the long term so designed, rather than
ad hoc site measures to reduce infiltration are important.
(f)
T&G and Taped Insulation
Potentially
a minor issue, but given higher priority becasue it is relatively easy to solve
and reduce airtightness and thermal insulation related risks.
Costs
It is difficult to ascertain any meaningful cost
implications with this detail because of the variety of curtain walling
systems available.
The measures outlined are fairly standard in most
installations and should in all cases represent no more than a re-iteration of
good or best practice. However, they could attract an additional cost where one
particular system did not address airtightness in one way or another.
Measures such as the additional efforts associated
with air barriers at the separating floor, eaves and flor / wall junction might
attract additional costs over that aspect of the original detail by
approximately 30% largely because of the additional labour and attention
required.
LOW PRIORITY
(g)
Membrane Seal between Floors
The
existing detail should provide a reasonable degree of airtightness, but this
measure will make the task conscious and effect a greater degree of separation.
(d) Foam
Filler
Should not
be required if the measures in (b) and (c) are completed, but an additional
measure that also has value in providing a backing to a continuous mastic seal
internally.
9.4 Index
(a) Airtight Performance Specification for
Curtain Walling
The de facto standard for curtain walling
air permeability that most curtain walling manufacturers comply with is the
CWCT (Centre for window and cladding technology) ‘Standard and Guide to Good
Practice for Curtain Walling’. This specifies a maximum air permeability of 1.5
m3 / hour/m2 @600pascals for an area of fixed glazing, and 2m3/hr/linear metre
of joint for opening panels. This is the same as the British Standard BS EN
12152:2002, category A4. However, the BS has a further category, AE that
achieves 1.5m3 /hour /m2 at a pressure differential of more than 600pascals.
Specification of this ‘exceptional category may be possible but it may mean a
reduction in choice as this is a more stringent level of testing. The rule is:
If wind load up to 2400kn then curtain walling to be tested to 600 pascals. If
wind load greater than 2400kn then test to wind load/4, e.g if 4000kn, test
curtain wall to 1000 pascals.
Maximising airtightness can be done by
having vulcanised welded joints to gaskets within the curtain wall frame,
instead of usual mitred ones. This should ensure that the unit its self is
airtight, although it is an expensive option.
(b) Mastic Bedded Fixings
Where membranes and components are
connected, it is often possible for thin - and often more or less invisible
gaps to be left between the joint. A continuous mastic seal used along the line
of any such mechanical fixing ensures that any minor cracks like this are
completely sealed.
(c) Additional Membrane Seal at Junction
Some Manufacturers (eg Schuco) supply as
part of their system an EPDM perimeter gasket seal that should be tied into
vertical DPM. Angle at jambs and loose dpm to wrap ensure good seal with EPDM.
This is a particularly good way to ensure airtightness at these critical
junctions because it requires a conscious task (sealing the membrane) to ensure
all ‘loose ends’ are firmly fixed, as opposed to leaving the airtightness to be
achieved through the use of applied sealants.
(d) Foam Filler to Internal Joint
Assuming that the seal mentioned above is
installed correctly this should not be required, but such a seal acts as an
additional check against air leakage and could be used as a backing strip against
which to seal a continuous mastic seal internally.
(e) Membranes to be Lapped and Sealed
Best practice in this regard - beyond the
correct use of Manufacturers’ overlap dimensions, proprietary tapes and other
accessories - is to run a layer of double sided tape between the membranes at
the overlap and run a tape over the leading edge of the outer sheet. In
addition, since many tapes tend not to last too well, it is advisable to ensure
that laps are made directly over supported areas (i.e. with solid materials
directly behind) and are held down positively with battens fixed through, or
some other ‘positive’ connection forming a mechanically tight, as well as an
adhesive seal. This may require consideration of lap positions early on.
(f) T&G Jointed and Taped Rigid
Insulation
Butt jointed insulation, even if installed
firmly may be subject to movement during the course of construction and over
time, and is unlikely to offer a continuous insulation layer in the long term.
Using t&g slabs overcomes some of this problem and taping the slabs ensures
that air leakage paths cannot form between the minute, but inevitable cracks
between the units.
(g) Additional Airtight Membrane
It is likely that the fireproof stopping will
not be able to create an adequately airtight seal and so this measure ensures
the task is performed consciously. Using a simple polythene membrane and
forming positive connections to the underside of the slab and the top of the
curtain walling ensures an airitight seal between floors and at the vulnerable
connection of curtain walling to spandrel panels
(h)
Localised Welding of Plates of Beam
It is practically very difficult to form an
airtight seal perpendicular to an ‘I’ beam or similar, expanding foam tends to
be used because no ‘built’ connection appears workable, nor cost effective.
Such ad hoc seals are unlikely to last in the long term.
Ideally plates should be welded to the beam
such that there is no air route along the length of the beam (a plate welded
perpendicular to the web and extending between the two flanges) and such that
airtight seals are easily formed around the beam as it passes the airtight
layer. Side plates fixed between flanges form a sort of localised rectangular
section which is more easily sealed. This makes the task more readily achieved
on site, and more durable in the long term.
9.5
Refurbishment of
Masonry
Building
Discussion
If the existing masonry fabric of a refurbished
building is in good condition, it is potentially simple to render it relatively
airtight if the details proposed - particularly the use of service voids - are
followed. All the work can be carried out internally and is simple to install
and check
In addition there is no cavity in this form of
constructin and this means ther are fewer opportunities for undetected
airways.
It goes without saying that any cracks or damage to
the existing fabric should be made good before installation of the internal
frame.
If there is enough space, it might be best to
retain all existing lath and plaster on ceilings and walls, ensure that it is
effectively sealed, and work inwards from there. Experience suggests that lath
and plaster itself is fairly airtight and removing it merely creates more
waste. One potential disadvantage is that in keeping the existing plaster, it
may not be possible to access the gaps behind which may run into floor voids
and partitions creating air leakage paths throughout the building.
A number of reviewers of this Guide commented that
it is more common to maintain a cavity between the existing wall and any
new-build internal leaf. The alternative proposed keeps to the same format as
the original, but the advantages of the use of a cavity are well understood.
HIGH PRIORITY
(a)
Membranes Lapped & Sealed
With only
one membrane to ensure airtightness it is crucial that laps and junctions are
conscientiously sealed.
(b)
Service Void
Use of a
service void means most if not all penetrations through the vapour control and
airtight layer can be avoided.
(c)
Joinery Edge Sealing Batten
If the
membrane generally is well sealed, the only other major area for infiltration
is the openings and the gap between the frame and masonry. If the windows can
be efectively sealed by (medium priority e) then this measure is not necessary.
(d)
Joinery Draughtstripping
A
particular issue with sash and case windows. It is important that seals can be
easily accessed for maintenance and replacement.
MEDIUM PRIORITY
(e)
Flexible Foam around Joinery
Gaps
around openings are common and neat, effective solutions can be difficult,
careful use of flexible foam enables effective and durable seals to be formed.
If this can be effectively achieved with the sash and case window then (f) is
not necessary.
(f)
Continuity at Openings
Continuity
between the framing sealant (m) and the membrane can be tricky and care is
needed to ensure a good, durable seal.
(g)
Backing Boards
Use of
backing boards makes installation of the membrane easy and thus less prone to
poor workmanship and subsequent failure.
Costs
The retention of the ceiling lath and plaster saves
approximately 24% of the costs of that element, while the addition of the
service void and vapour check represents a 18% cost increase, thus, without the
addition of the breather membrane over the ceiling joists (a medium priority
measure) there is a cost saving to complement the increase in ease and cost of
services installation.
The breather membrane represents a 13% increase in
cost and therefore tips the balance of the ceiling cost overall.
The addition of the OSB backing board and service
void to the walls constitutes around a 46% increase in cost of the wall, the
majority of which (33%) is made up by the OSB, so perhaps a cheaper, yet firm
backing board might alleviate the cost burden. The addition of the OSB layer
to form a service void beneath the floor boards would add approximately one
third to the cost of the original detail.
Double mastic sealing of the skirting boards adds
approximately 50% to their installation cost, although their overall costs are
small in the overall picture.The sealing of the vapour control layer above and
below the intermediate floor should not attract any additional cost if assumed
to be part of a standard, if careful installation. Measures to help seal around
the window would add marginally to a standard installation cost.
MEDIUM PRIORITY
(a) Batten
Seal at Corners
A version
of (b) but worth particular mention as these junctions are particularly
important to seal well.
(b) Keep
Existing Lath and Plaster
Really a
version of (e) except in this case we suggest retaining the existing firm base
of lath and plaster against which to affix the vapour control layer.
(c)
Plasterboard Penetrations
If the
airtight layers are sound then this should not matter, but still worth
attention.
(d)
Membrane Over Roof Insulation
Protects
installed insulation from disruption and provides a secondary layer at this
important area.
LOW PRIORITY
(a)
Silicone to Joinery Externally
Should be
standard practice, but forms useful role in airtightness as well as weatherproofing.
(b) Mastic
to Skirtings, Linings, Cornices
Not
necessary if the airtight layer is sound but worth attention in these examples.
9.6 Index
(a) Breather Membrane over Insulation
In well ventilated loft areas, loose
insulation may become dislodged by air movement. This precautionary measure
ensures that the initial fully fitting installation of batts against joists etc
is maintained over time, reduces dirt and debris entering and provides an
additional airtight layer (which is useful since the loft is ventilated) whilst
allowing for vapour egress into the ventilated space.
(b) Membranes to be Lapped and Sealed
In order to create airtight layers, it is
important that laps are rigorously sealed. Best practice in this regard -
beyond the correct use of Manufacturers’ overlap dimensions, proprietary tapes
and other accessories - is to run a layer of double sided tape between the
membranes at the overlap and run a tape over the leading edge of the outer
sheet. In addition, since many tapes tend not to last too well, it is advisable
to ensure that laps are made directly over supported areas (i.e. with studs or
dwangs directly behind) and are held down positively with battens fixed through
forming a mechanically tight, as well as an adhesive seal. This requires
consideration of lap positions early on if extra framing or subsequent
battening is needed.
(c) Vapour Control Layer over Existing Lath
and Plaster
Rather than remove the existing lath and
plaster ceiling, this detail saves a little money, time and resources by
reusing the existing ceiling as a backing to the installation of the vapour
control layer (refer also (e)) Plaster need not be repaired if damage is
localised and does not threaten the integrity of the vapour control layer.
(d) Service Void
The principal advantage of a service void is
related to functionality and maintenance of services over time, but a secondary
advantage which relates directly to airtightness is that since all services may
be incorporated within, that is, on the inside of the vapour control layer,
there is no need to penetrate the layer at each and every service installation,
thus significantly cutting down on the myriad potential gaps that are typically
formed and either left, or made good which is time consuming and costly.
(e) Fix Airtight Membranes to Firm Backing
Boards
In many situations membranes required for
vapour control and airtightness are installed unsupported and are thus
susceptible to pressures from both sides, leading to the membrane breaking free
of its fixing and creating holes in the airtight layer. Ideally, membranes
should be fixed against a firm backing board by way of protection against
damage of this nature.
(f) Mastic Both Edges to Skirtings, Reveal
Linings etc.
Where the corner junction behind has been
carefully sealed then this measure may not be required, In the examples shown
on this construction, this particular detail is not critical but is nonetheless
valuable in helping to ensure a good seal at all points.
(g) Airtight Layer Taken Behind Batten at
Corners
As noted in (b) above, the best airtight
seal is a positive and mechanical one such as shown here whereby at corners and
edges, a membrane is not only lapped and taped against the adjoining surface,
but held firm by a batten fixed through. This overcomes any potential adhesive
failures or tears in staples or tacks etc. In the ceiling junction where the
plasterboard layer must be continuous for reasons of fire spread prevention, it
is also advisable to install laying tape at the junction between the
plasterboard and the wall to ensure an airtight seal here also.
(h) Seal all Penetrations in Plasterboard /
Internal Lining
Even with the use of airtight ooutlet boxes
there will be inevitable penetrations such as ceiling pendants, pull cords,
recessed fittings etc. which must be made good manually, typically with mastic,
and in this case, with a suitably fireproof mastic to maintain the fire
barrier.
(i) Ensure Membrane is taken into Opening
Reveals, Taped and Sealed and Made Continuous with Opening Seals, it is typical
at openings to allow the membrane to run across the opening initially, then
form a star cut into the opening, folding over the sections of membrane and
trimming as necessary. In these cases, there are inevitable gaps in the
airtight layer at the corners of the opening, and it is important to ensure
that these are made good before subsequent installation of joinery etc.
(j) Sealing Batten
This detail may be considered as an
alternative, or ideally as an additional measure with (k). Since it is possible
that replacement sash and case windows cannot be easily sealed around their
perimeter (they are often ‘open’ around the outer edge) it may be necessary to
use this detail which creates the airtight seal on the inside of the frame
rather than ‘in line’ with the frame as noted below.
(k) Flexible Foam Sealant around Joinery Insertions
Gaps around openings are one of the most
common of infiltration paths. They range from 0 to 20mm, which is too large to
be filled by mastic. Compressible flexible foams are ideal for this application.
Ensure that the airtight membrane meets the seal on both sides to maintain the
airtight layer overall.
(l) Draughtstripping of Openings in Joinery
Draughtstripping of joinery comes in many
forms. It appears that synthetic rubber or elastomeric tubular seals work well,
creating good seals with minimal compression. It is important that seals are
unaffected by paintwork and subsequent decoration, or are easily accessible and
removable. This is important so that seals can be replaced as they start to
fail to maintain the airtight layer. Brush seals are likely to be used in sash
and case windows.
(m) Silicone Sealant to External Window Surround
Some form of neat and potentially paintable
edge seal will be required externally
.
(n) Breather Membrane Instead of Netlon
Notwithstanding the air barrier placed
above, mineral wool is permeable to air movement and so replacing the netlon
with a vapour permeable but airtight breather membrane reduces air movement in
the insulation, improving insulation levels and reducing the risk of air
leakage generally.
9.7 Concrete Frame and
Panel
Discussion
Concrete panel construction represents a
potentially good airtight form of construction. This is because the panels
themselves are essentially airtight and being large, have fewer gaps which must
be sealed. Being fairly predictable in terms of thermal and structual movement
they are easy to seal well, and the only areas of concern then are the service
penetrations and junctions with openings. With care and attention in these
areas, a very good overall airtight external envelope is easily within reach. Having
said that, in some early examples of this building type, the sealants between
panels have failed, highlighting the vulnerability of the system to such
failure and the importance of correct specification and application.
A number of systems are available but the
principles outlined for the improvement of the system chosen are widely
applicable. Where two leafs of concrete panel are used, it is unlikely that the
outer layer will be used as a rainscreen layer, but this is sometimes done,
and in these cases the airtightness of the internal layer of panels becomes
critical, and may be augmented by the application of a vapur control and
airtight membrane on the inner face of the insulation, applied to the panels
before the insulation is installed. Guidance on the application of this
membrane, and on potentially more airtight forms of insulation may be found
In Sweden, concrete panels are sometimes sealed to
each other using polyurethane foam which is claimed to increase the
airtightness levels, but there does not appear to be any evidence of this form
of sealant in the UK.
HIGH PRIORITY
(a)
Integral Beam and Internal Panel
Important
because this reduces the number of joints and simplifies construction.
(b)
Sealing of all Penetrations
Care and
attention to detail at all services and other penetrations is vital, most pressure
tested panel buildings suffer leaks at these locations.
(d)
Sealing around Windows
The other
major source of leaks in concrete panel buildings apart from (b) above, care
and attention to detail along all joints needed.
(c) Screed
Edge Strip and Seal
Ensures
that air does not leak between floors around the perimeter and at other floor
penetrations and breaks in the screed.
MEDIUM PRIORITY
(a)
Accessible Draughtstripping
It is
important that the draughtstripping is accessible since it is likely that it
will not last as long as the windows themselves and require replacement.
(b)
Membrane around Windows
Required
for vapour and air leakage control, this also required attention and inspection
and can be seen as complementart to the mastic / silicon selants
(c) Double
Silicon Seal to External Panels
Double
silicon sealant lines in the external panels is normally standard practice, and
is typically good enough to ensure that the outer panels provide an effective
airtight seal throughout.
Costs
The alternative specification highlights best
practice installation and should not incur any additional costs. The design of
the panel construction system itself would dictate any cost difference.
LOW PRIORITY
(h)
Membrane Under Roof Insulation
May not be
required if the screed below is fully sealed against vapour and air flow, but
given the typical number of penetrations in a commercial roof screed, the
addition of a dedicated membrane may be considered advisable.
10 Useful Names
Air
barrier
An air barrier comprises materials and/or components, which are air impervious
or virtually so, separating conditioned spaces (heated), from unconditioned
spaces (unheated) e.g. the outer envelope of the building.
Air
change rate
The rate at which outside air enters a space divided by the volume of that
space. This is expressed as ach (air changes per hour).
Air
curtain
A stream of high velocity, temperature-controlled air which is directed across
an opening. It enables control of conditions in a space, which has an open
entrance.
Air
exfiltration
The uncontrolled outward leakage of indoor air through cracks, discontinuities
and other unintentional openings in the building envelope.
Air
infiltration
The uncontrolled inward leakage of outdoor air through cracks, discontinuities
and other unintentional openings in the building envelope.
Air
leakage audit
The inspection of materials and components, between conditioned and
unconditioned spaces to try to establish where major discontinuities in an air
barrier system might exist.
Air
leakage index
The leakage of air (m3.h-1) in or out of a building space, per unit area (m2)
of envelope (excluding ground floor area ,except for non-ground supported lower
floors) at a reference pressure of 50 Pa between inside and outside the
building.
Air
permeability
The leakage of air (m3.h-1) in or out of a building space, per unit area (m2)
of envelope (including ground floor area) at a reference pressure of 50 Pa
between inside and outside the building.
Air
leakage rate
The leakage of air (m3.h-1) in or out of a building space, per unit volume (m3)
at a reference pressure of 50 Pa between inside and outside the building.
Air
leakage path
A route by which air enters or leaves a building or flows through a component.
Airtightness
A term describing the leakiness of a building. The smaller the leakage for a
given pressure difference across a building, the tighter the building envelope.
Airtightness
layer
A layer built in to the external envelope to minimise air infiltration/exfiltration.
It may consist of a wide range of materials (for example,sealants, gaskets,
glazing or membranes) and should be continuous to be effective.
Breather
membrane
A water-resistant sheet which allows transmission of water vapour, but which
provides resistance to airflow.
Conditioned
zone
The occupied zone in a building requiring heating or cooling and normally
bounded by an airtightness layer.
Draught
Excessive air movement within the conditioned zone, which may cause discomfort.
Draughtproofing
Filling gaps between opening parts of components and their frames.
Envelope
area
The boundary or barrier (m2) separating the interior volume of the building
from the outside environment. This includes the area of the external walls,
roof and depending upon the air leakage parameter specified the area of the
ground supported floor.
Fan
pressurisation test/Air Leakage test/Air Tightness Test
A method of testing air leakage of a building. It allows airflow and pressure
difference across the envelope to be measured and an estimate of leakage to be
obtained.
Infiltration
rate
The rate at which outside air infiltrates a building or a room under natural
meteorological conditions (normally expressed in air changes per hour or litres
per second)
Infrared
camera
A camera sensitive to the infrared part of the spectrum, which can be used to
‘see’ locally cooled areas on the internal surfaces or heated areas on internal
and external surfaces of the envelope of a building.
Minimum
ventilation requirement
The minimum quantity of outdoor or conditioned air which must enter a building
to maintain an acceptable indoor air environment for occupants.
Natural
ventilation
The movement (caused by wind and outside temperature) of outdoor air into a
room or space through intentionally provided openings, such as windows and
doors and non-powered ventilators.
Smoke
test
A building (or parts of it) is filled with smoke using smoke machines and then
pressurised to force the smoke through gaps in the building envelope.
Smoke
tube/pencil
A hand held device which produces smoke in small quantities for more specific
identification of leakage paths within a building under pressurisation or
depressurisation, or under natural infiltration.
Stack
effect
Air movement through a building caused by differences in the density of air due
to temperature differences between the air inside and outside of the building.
Thermography
The use of thermographic cameras sensitive to infrared radiation to identify
thermal weak spots in the envelope of the building and to help identify air
leakage paths through gaps and cracks in the building.
Vapour
control layer
A layer impervious to water vapour and usually enclosing an occupied space.
Ventilation
Supplying or removing air, by natural or mechanical means, to or from a space.
Air
Pressure Testing FAQ - Page Topics
Air Testing | Air
Pressure Testing | Conducting
Air testing | Technical
Air Tesing | Air
Testing Solutions | Diagnosing
Air Testing Problems
Air Testing Procedures
| UK Air Testing Services
| Air Testing Theory
| Air Testing
information for Architects | Contact
Air Pressure Testing UK