Air Tightness: A
general overview to testing and design
1.0 Key Principles
1.
Testing procedure is set out in CIBSE TM 23 and the ATTMA TS1
2.
A air tightness test involves sealing all ‘normal’ gaps such as vents and
pressurising or depressurising the building. The level of fanpower required to
maintain the pressure differential indicates the ‘leakiness’ or ‘permeability’
of the building.
3.
Air tightness/air leakage tests are typically followed by an air leakage/air
tightness audit (using smoke pencils, for example) to expose and make visible
the various air leakage routes.
4.
Where projects comprise large quantities of a single component, component
testing in the laboratory may be appropriate as well as on site element
testing.
2.0 Climatic conditions
As
mentioned in Chapter 1, the raised pressure differential of 50 Pascals created
during an airtightness test is quite small. Whilst this is adequate to overcome
most of the common pressure differential anomalies, such a small differential
is vulnerable to larger pressure differences created by climatic conditions.
Air
leakage tests/air tightness tests require calm days – i.e. a reading on the
Beaufort Scale of 3 or less (3.4 to 5.4 metres per second wind speed at 10 m
above ground) This corresponds to a gentle breeze with leaves and small twigs
in constant motion. In winter conditions, and on exposed sites therefore
testing may not be possible, although it is often possible to make allowances,
so long as these are carefully recorded during the Air leakage tests/air
tightness tests.
3.0 The Test itself
Guidance
on testing buildings for Air leakage /air tightness is contained in CIBSE
Technical Memorandum TM23 Testing Buildings for Airtightness and in BS EN
13829: 2001. All accredited air tightness testers test to the guidelines
contained in the BS EN and within the ATTMA TS1
Essentially
the air tightness/air leakage process is one of pressurising or (less commonly)
de-pressurising the inside of the whole building, and of measuring the rate at
which air needs to be blown or sucked to maintain that pressure differential; a
building suffering from high amounts of air leakage will equalise readily and
require a greater measurable effort to maintain the 50 Pascal differential,
while a air tight building will easily contain the enforced differential and
require little additional input.
The
pressure difference is induced by one or more calibrated fans that are normally
mounted within a suitable doorway. An adjustable door panel system, sealed
around the edges is used which can also be connected to large external fans via
collapsible ductwork if required. The rate of the fan or the volume flow of air
through the fan can be understood as the rate of air entering / escaping
throughout the remainder of the building envelope.
Buildings are air tightness tested/air leakage tested in such a way as to
recreate ‘normal’ conditions. Doors and windows are closed; trickle ventilators
closed, extract fans and such like are closed but not sealed. Internal doors
are wedged open. All of this must be actioned prior to the air leakage test/air
tightness test
If
the building is under construction, Air tightness testing/air leakage testing
can be undertaken during working hours, but sometimes this is not
practical so some scheduling of work needs to be thought through in advance.
With all external doors and windows sealed shut, some work becomes impossible
(such as work with solvents requiring ventilation) and internal trades are
normally ‘sealed in’ for a short time, where they can carry on undisturbed
throughtout the air leakage/air tightness test
In
existing buildings, Air leakage tests/air tightness tests are normally carried
out when the building is unoccupied if possible because of the disruption.
4.0 Air Leakage Audits
The
air leakage test/air tightness test quantifies the rate of air leakage through
the envelope as a whole, but it cannot locate the air leakage paths. Where
remedial work is required therefore, air leakage/air tightness tests are
followed by a range of auditing techniques designed to identify the specific
places where air is leaking.
In
many cases a simple visual inspection may be sufficient – especially if
undertaken by someone with experience of the likely locations of air leakage.
However,
most air leakage routes are difficult or impossible to spot without visual aids
during the air leakage /air tightness test. One common technique is to use
smoke tracers – smoke pencils or smoke machines. These render the air paths
visible in certain situations. The building may be positively pressurised
during the air leakage/air tightness test and the leaks witnessed externally,
or, more usually, negatively pressurised while a smoke pencil is drawn over
likely gaps and defects which become visible as the smoke is sucked inwards.
Another
technique, which has certain advantages and disadvantages compared to smoke
tracing along with an air leakage/air tightness test, is the use of an infrared
camera during a Thermographic test. Used either externally or internally, these
thermographic cameras register the radiant heat levels of surfaces and so are
able to ‘see’ for example, where cold air is cooling the fabric around a gap
internally, or conversely where warm air is escaping and heating the colder
materials on the external face.
To
work effectively, there needs to be a recognisable difference between the
internal and external ambient temperature, so before any heating has been
installed and on a warm summer’s day thermography testing may not be effective.
Similarly on warm and sunny days, sunshine on external surfaces can distort the
true situation so it is better on such days to wait until early evening.
Conversely, rain on external surfaces can be equally distorting of the true
thermal situation. However the
Thermographic cameras are useful in identifying problems at high level
or difficult to reach areas, and are also very helpful in identifying other
construction defects such as poorly installed (or non-existent!) insulation
within the fabric.
On
larger commercial buildings, airtightness testing/air leakage testing may be
undertaken at the same time as ‘standard’ ventilation system commissioning and
associated studies, but these are not discussed as part of this guide.
5.0 Component Testing
A
distinct aspect of overall air tightness testing is the individual component
test. This may be undertaken quite separately, in the laboratory or by the
manufacturer of a particular component. Such air tightness sampling tests may
be deemed necessary on a large project where large areas of one particular type
of component, for example curtain walling, are to be specified, Insitu element
testing involves isolating the area within a temporary sealed compartment,
which is then pressurised, and the air leakage related to the area of interest
assessed. In this way sample areas of a building may be air tigtness tested
using smaller fans as required.
5.1 Concrete frame and panel
1 Introduction
As thermal
insulation levels have risen in the last few years the proportion of energy
lost to draughts has increased to the extent that now in some cases around half
of all heat losses are due to air leakage across the building fabric. Given
that approximately half of all energy used in the
The
situation is such that further increasing thermal insulation levels would be
largely unproductive unless air tightness is conscientiously addressed. Air
leakage has been shown to reduce the effectiveness of thermal insulation by up
to 70% and so it is clear that if energy efficiency is to be improved in
buildings, the next efforts will have to focus on air tightness/air leakage
testing.
Many
people make the mistake of thinking that an airtight building is necessarily a
‘stuffy’ building. This is not the case. All buildings have to be ventilated
for health and comfort and airtight buildings are no different. An adequate
ventilation system (which may well include openable windows as well as fans
etc.) has to be planned for every building. The difference will be that a great
deal of unplanned air leakage needs to be stemmed.
The
additional costs of creating an adequately airtight building can be
negligible, but even where costs are increased, these can be more than offset
by a reduction in the capital cost of heating and ventilation equipment, not to
mention the long term savings in energy.
Given that
the vast majority of building stock is existing, a great deal of attention will
need to be given, in the foreseeable future, to remedial works to existing
buildings. This guide specifically includes examples of good and best practice
remedial work in terms of air tightness and shows that such works can offer
substantial benefits without undue disruption or cost.
Air
Pressure Testing hopes to provide practical guidance on how to save energy and
costs and protect building fabric. On the basis that prevention is cheaper and
easier than cure, one purpose of this guide is to enable Designers to design
inherently more robust and durable solutions which avoid costly and time
consuming remedial works on site after a potential air leakage failure
The
general guidance here is firmly focused on the idea of practical design and
detailing, and should be read in conjunction with other guidance on sustainable
design, energy efficiency and air tightness where necessary to provide an
overall design framework. The details provided have been fully costed, tested
and subjected to a Defects Liability insurance assessment. They are offered as
viable alternatives to standard details, and illustrate the possibilities that
exist. It simply remains for you, the reader, to apply them appropriately in
the context of your next project prior to your air leakage test/air tightness
test
Aims of this Guide
• To highlight
benefits of air tightness which include both energy and cost efficiency,
improved comfort and reduced risks of damage to building fabric
• To improve
awareness of the need for air tightness in construction
• To promote detailing and specification
solutions which create airtight and efficient buildings thus reducing the need
for remedial works after air leakage failure- ‘prevention rather than cure’
• To show that
new build and remedial air tightness are achievable without undue cost
penalties to construction works due to multiple air leakage failures
• .and in this
way to help to ‘mainstream’ the good and best practice outlined in the document
Target
audience
This Guide will help all those who wish to improve
the airtightness/air leakage rate and energy efficiency of buildings through
their construction, e.g:
• clients
–building owners and users, principal and specialist contractors, interior
designers architects and technicians, structural engineers, building service
engineers, building surveyors, quantity surveyors/ cost consultants,
maintenance and facilities managers, project managers , planning officers and
building control officers, funding bodies and their professional advisors,
government and non-governmental agencies
How to use
this Guide
This Guide is divided into six sections. The first
two sections provide an overview of the issues surrounding air tightness.
Sections Three, Four and Five describe the requirements for the design process,
the procurement and the air leakage/air tightness testing involved in
designing for airtight buildings.
Section Six provides a number of representative
details which have been optimised in terms of airtightness. These are compared
with standard details for a variety of construction types, and costed. This
section will be primarily of interest to the design team. It should be read in
conjunction with sections Three, Four and Five in particular, as all details
must be placed in a suitable context.
6.0 The Context
Key
Principles
1. Most UK
construction is ‘leaky’ and wastes energy and money. Building airtight
buildings can save energy and money, improve comfort and reduce the risk of
damage to building fabric.
2. Airtight building will
NOT mean ‘stuffy’ buildings. Good ventilation is vital for health and comfort -
it is the UNPLANNED leakage of air that we are aiming to stem.
3. Legislation
is slowly catching up with best practice in Scotland, the UK and elsewhere and
we can expect a greater emphasis on airtightness in all types of construction
in due course.
4. Good and Best Practice
Targets of air tightness/air leakage have been set for many types of buildings
and are easily achievable.
6.1 Infiltration, Ventilation and
Airtightness
Air
infiltration (air leakage) is the
uncontrolled flow of air through gaps in the fabric of buildings. It is driven
by wind pressure and temperature differences and as a result is variable,
responding in particular to changes in the weather. Infiltration (air leakage)
levels are strongly affected by both design decisions and construction quality.
Ventilation,
on the other hand, is the intended and controlled ingress and egress of air
through buildings, delivering fresh air, and exhausting stale air in
combination with the designed heating system and humidity control, and the
fabric of the building itself.
Whilst
some unwanted air infiltration (air leakage)
will at times aid comfort levels, it is not reliable and moreover
brings with it a range of significant disadvantages such as high levels of
heat loss, reduction in performance of the installed thermal insulation, poor
comfort, poor controllability and risks to the longevity of the building fabric
itself. It cannot be considered an acceptable alternative to designed
ventilation. Infiltration (air leakage) needs to be reduced as much as possible
if we are to create efficient, controllable, comfortable, healthy and durable
buildings. This can be achieved by delivering airtight buildings that pass the
air tightness/air leakage tests first time.
Air
tightness is a term used to describe the ‘leakiness’ of the building fabric.
An airtight building will resist most unwanted air infiltration (air leakage)
while satisfying its fresh air requirements through a controlled ventilation
strategy. Most existing buildings, even those built recently, are far from
being airtight and because of unwanted air infiltration (air leakage) generate
huge costs to owners and occupants, in environmental, financial and health
terms.
It is
important to emphasise the distinction between infiltration (air leakage) and
ventilation, because while the primary purpose of this document is to show how
buildings can be designed and constructed to be airtight, it is equally
important to stress that good levels of ventilation and a clear ventilation
strategy will be required in every case. As the saying goes: ‘build tight,
ventilate right.’
6.2 Why Build Airtight?
Legislation
At a rather prosaic level, the issue is important
because it is now part of the Building Regulations in England and Wales
concerning non-domestic new buildings over 500 sqm in area, and is likely to
affect a wider range of buildings soon. Whilst the initial targets set for
airtightness of buildings are easy to achieve, it is equally likely that once in
place, those targets will be ratcheted up to create ever more airtight and
efficient buildings in the UK, in line with many of our European neighbours.
Energy and Cost Saving
Typically, the largest heat losses in most
buildings are related to levels of thermal insulation, followed by those
related to infiltration (air
leakage), followed by those related to inefficient plant. Quite
rightly therefore, most efforts to save energy and costs have until recently
been directed at increasing thermal insulation levels. But as these levels
have risen, so the relative contribution of infiltration (air leakage) has increased to the point
where it can represent around half of all heat loss in a building. In highly
insulated buildings, the percentage may be higher.
This is reflected in the fact that total space
heating costs in an airtight building may be as much as 40% less than in a
leaky one
We are at the stage where it is likely that any
further increase in thermal insulation levels would be ineffective until levels
of air tightness in construction have improved considerably.
Space Heating System Reduction
Clearly there is potential to reduce the capacity
of space heating systems sized to cope with current levels of heat loss if
those levels can be reduced by a half or more. In addition, airtight buildings
are more predictable in terms of environmental control and the capital cost
savings of installing smaller heating plant may be augmented by reduced plant room
sizes in certain cases and particularly by reduced running costs in the longer
term. As well as reducing the need for heating plant, airtight buildings offer
much greater potential to respond positively to the local external climate
through passive, or climate responsive design strategies such as natural
ventilation, day lighting, the use of thermal mass and passive solar gain.
Energy savings, capital and running costs, along with CO2 emissions
can thus be further reduced.
Comfort and Control
As noted above, airtight buildings are not as
affected by variations in external conditions. This makes them easier to
control from an Engineer or Designer’s point of view, but it also makes them
more comfortable from the point of view of the occupant.
In buildings with high levels of infiltration those
occupants near draughty windows, for example, will suffer the cold,
particularly on windy days, whereas those elsewhere may well suffer from too
much heat locally as the system tries to raise the temperature overall. Those
who try to achieve comfortable levels through the use of the provided
ventilation controls will find these to be relatively ineffective, whereas in
more airtight buildings greater levels of control and comfort generally are
achievable and local control and variation by occupants can have a more direct
effect. In one example of an existing superstore, the ambient temperature in
the store was raised by 5oC after the store had been sealed. Complaints
by occupants in leaky buildings are common, and remedial measures are usually
difficult and expensive.
Deterioration of Fabric
Leaky buildings allow cold air in through the
construction causing discomfort, they also allow warm (and often moist) air
out, causing heat loss. This warm and often moist air can find itself in colder
parts of the outer construction where it can cool, and the moisture in the air
can condense, leading to a buildup of moisture. This in turn can lead to:
• decay of organic
materials such as timber frames
• saturation of
insulating materials thus reducing their insulative effect (which increases
heat loss further)
• corrosion of
metal components
• frost damage
where moisture has accumulated on the cold side of the insulation.
6.3 Legislation
In England
and Wales the relevant regulation on air tightness is contained within Approved
Document L1 for dwellings and L2 for non-domestic buildings (2006). There is
general encouragement to consider air tightness issues, with a target air
permeability for all buildings of 10 m3/hr/m2 envelope area at 50 Pa. In L2, buildings with a floor area
of greater than 500 m2 are required to be tested if approved details are not
used. Further tightening of the regulations are due in 2010.
Proposals
for changes to the Energy standards were issued to public consultation in March
2006, including guidance that air tightness testing would be required if the
calculation of energy performance included air permeability rates lower than
10m3/m2h at 50 Pa.
6.4 Measurement
A range of
units for measuring air tightness/air leakage have been used in the past and
this can complicate matters. However, one method only – “air permeability” - is
the measure used in European Standards, the new editions of the various UK
Building regulations and in CIBSE’s TM23 Testing methodology and has been used
throughout this document. The Air Permeability is defined as the volume flow in
cubic metres of air per hour per square metre of the total building surface
area (including the floor) at 50 Pascals pressure differential, expressed in m3/hr/m2 @ 50 Pa.
The main
difference between the air permeability and previous practice in the UK is the
inclusion of the non-exposed ground floor in the calculation of the ‘total
surface area’ of the building. The difference between the new measurements and
older ones tend only to be marked therefore where there are large volumes and
ground floor areas.
Of the
range of measurements used previously, the “Average Air Leakage Rate (or
Index)” is similar to the “Air Permeability” except that non-exposed floors are
excluded from the measurement. Another common expression is the “Air Changes
per Hour at 50 Pascals (ACH @ 50 Pa). This is a useful measurement in
particular because, when divided by twenty, it gives an approximate value of
the natural infiltration rate of the building at normal atmospheric pressure,
which can then be used to help size heating and ventilating plant etc.
Yet
another measurement is the “Equivalent Leakage Area” (ELA) at 50, 10 and/or 4
Pascals. This figure gives a representation of the sum of all of the individual
cracks, gaps and openings as a single orifice and helps to visualise the scale
of the leakage problem. The main problem of changing the measurement technique
is the ability to compare data
The
standard pressure differential used is 50 Pascals. This is not in fact a very
large pressure differential and corresponds to the pressure exerted by a column
of water 5mm high. Compared to the fact that buildings can withstand wind
induced pressures of at least 500 Pascals, this seems insignificant, but it is
larger than wind induced pressure on a calm day, and by testing and quoting air
leakage figures at 50 Pascals, inaccuracies are reduced and repeatability is
improved.
6.5 Targets
As noted
above, the only ‘official’ guidance in the UK applies in England and Wales and
relates to non-domestic buildings over 500 sq.m in area. As can be seen from
the table below, the target of 10 m3/hr/m2 at 50 Pa. is relatively easily achieved compared to the good
and best practice noted in the 2000 document by CIBSE, TM23. This sets out the
air tightness/air leakage testing methodology which is the de-facto methodology
now followed in the UK.
A number
of air tightness experts believe the stated targets are inadequate when
compared with the overwhelming need to address carbon emission reductions, and
the potential to do so through air tightness measures. For example, the house
illustrated to the right was built in 1992 for the same cost as nearby houses
and improved upon the standards noted above by two thirds.
Building Type Air Permeability (m3/hr/m2 at 50 Pa)
Good Practice/ Best Practice
Dwellings 10.0/ 5.0
Dwellings (with balanced mech.
vent.) 5.0/ 3.0
Offices (naturally ventilated)
7.0/ 3.5
Offices (with balanced mech.
vent.) 3.5/ 2.0
Superstores 3.0/ 1.5
Offices (low energy) 3.5/ 2.0
Industrial 10.0/ 2.0
Museum and Archival Storage 1.7/ 1.25
Cold Storage 0.8/ 0.4
7.0 Designing for Airtightness
7.1 Key Principles
1. A Performance
Specification is a crucial document for establishing the appropriate targets
for airtightness, along with the methodology for achieving it, and the roles
and responsibilities of those involved.
2. Conceiving of
a building in zones and air barriers will help all involved to visualise the
task.
3. Air barriers
must be impermeable, continuous, durable and accessible. They should be
supported by positive mechanical seals where possible.
4. The simplest
solutions will be the most buildable and durable.
5. A culture of
airtight construction does not yet prevail and until it does, it may be
necessary to follow up targets with specific details and specifications, along
with guidance on the process of implementing the necessary level of co-ordination
and attention to detail.
Unlike
design for deconstruction (the subject of the first in this series of SEDA
Guides) and the forthcoming guide on chemical-free design, the design of
airtight buildings cannot be left to the specification and details, at least,
not until the industry as a whole recognises the need and has sufficiently
widespread experience. For the next few years, it will be necessary not only
to provide careful details and performance specification, but also to develop
thorough inspection and testing regimes, hence the need for Chapters 7.4 and 7.5
of this guide.
7.2 Performance Specification
The
Performance specification may be the only document needed by the Architect /
Designer / Client if the building is to be procured through Design and Build
or similar route. However, it is more likely to be part of a suite of documents
including detailed drawings.
The
performance specification allows appropriate targets to be set for the project,
along with a description of how the process is to be conducted, in terms of
scheduling, audits and testing, and potentially remedial works. Given the
increasing use of specialist subcontractors, particularly in larger projects,
it is also critical that the performance specification sets out both the
responsibility for, and constructive guidance regarding the co-ordination of
trades with respect to the final air permeability of the completed envelope.
Zones and Barriers
Once
appropriate targets have been set for the project, the next task is to identify
zones which require greater or lesser airtightness levels. Ideally, these
zones need to be identified on a drawing which also identifies the specific air
barriers in red.
For
example an industrial unit with office space is divided into five separate
zones, and air barriers are identified as required. Such a drawing, however
diagrammatic initially, helps to conceive of the subsequent specification and
detailing needs, giving an overview of the problem.
Heated
zones need to be kept separate from unheated zones such as roof voids, delivery
bays etc. whilst service shafts may require particular attention. Boiler rooms
with large flues and intake vents may need to be separated.
Entrances
are often significant sources of draughts. Lobbies with doors set apart by
around 4m, so that one door closes before the second is opened, can be
effective, whereas in highly trafficked areas revolving doors are likely to be
preferable. Tall buildings, with atria, stairways and service shafts all of
which rise through the building can be prone to ‘stack effect’ air movement
whereby warm air rises, dragging in cooler air from outside at the lower levels
creating more acute air leakage problems. A number of tactics may be employed
to reduce the effects, but in any event issues of airtightness are likely to be
highlighted in these cases.
7.3 Design
With the zones and air barriers located, it is
necessary to design the air barriers themselves.
To be effective, the air barrier must:
• be made of
suitably air impermeable materials;
• be continuous
around the envelope or zone
• have
sufficient strength to withstand any pressures created by wind, stack effect or
air control systems
• be easily
installed
• be durable
• be accessible
for maintenance / replacement if appropriate
The last of these is important since there is
evidence that the airtightness of some constructions will tend to decrease
over time and in particular the first period after completion.
There are a number of strategic measures which can
be employed to simplify the business of designing an airtight building. Since
service penetrations in and out of a building provide a major source of air
leaks, one strategy is to collect all such penetrations into one accessible
area.
In construction types such as steel and timber
frame, it is usually wise to employ a specific membrane or layer as the air
barrier, rather than rely on sealant between, for example, the sheathing
boards. Such a membrane can usually double up as the vapour barrier if used
internally and gives the Designer the opportunity to consider and address
airtightness explicitly, rather than as a function of other elements. Bear in
mind that most membranes are flimsy and will need support in all areas.
Another strategy is to employ service voids.
Creating a service void internally allows for alteration and maintenance of
services and finishes without recourse to penetrations through the air
barrier. This allows for long term good performance in contrast to membranes
which are liable to penetration at all service points, necessitating careful
sealing of each and every penetration, not only initially, but over the years
of alterations and maintenance to come.
Generally,
it is better to conceive of the joints in airtight layers as ‘positively’
connected, anticipating differential movement and decay of adhesive or
chemical bonds. For example, where different components of a curtain walling
system are liable to differential movement, it is clear that a joint whereby
the two components are held together with a positive mechanical connection
across a compressed gasket is likely to remain airtight longer that a simple
butt joint with a mastic sealant between.
Finally it is clear that complex solutions to
airtightness are likely to be more prone to poor execution and potentially to
greater vulnerability to differential movement, failure of sealants,
dislocation of components and so on. It is important therefore to aim for the
simplest solutions to providing a robust airtight layer, using the fewest
separate materials, junctions and penetrations, and the easiest installation
and maintenance.
It is
worth making a point of considering each and every specified component with
regard not only to its own intrinsic airtightness characteristics, but with
regard to the connections between it and adjacent components. It is important
to provide explicit details and guidance at specific, and particularly tricky
detail areas. On design and build contracts it may be necessary to allow for
some form of review of proposed solutions and procedures.
The following provide a few examples whereby
airtightness can be simplified at the earliest design stages.
However good the workmanship, blockwork on its own
can never be considered airtight. Once plastered, on the other hand, it may be
considered extremely airtight, with concern only for those edges and corners
where cracking or gaps can appear. This may be contrasted with the more common
practice of drylining block walls with plasterboard on battens or dabs.
Design & Detailing for
Airtightness
Services
Zones or Rooms enable a range of services to be collected together before
exiting the building, allowing most of the penetrations in the external fabric
to be grouped and sealed effectively.
Service
voids enable cables and pipework to be installed and altered without needing
to penetrate the air barrier. Note however that if they are not run in conduit,
protection may be needed against subsequent fixings. Source: C. Morgan
Positive physical connections are
to be preferred over any other joint such as one relying on adhesives. In the
timber frame example shown the air barrier membrane is shown lapped and sealed
with mastic over a firm background (boards with stud behind) and with a
positive mechanical fix - a batten - fixed over the top and through to the
stud.
Trinsically non-airtight block wall behind, this
form of construction typically gives rise to a wide range of air leakage paths
behind the boards and into floor, partition wall and ceiling cavities. From the
perspective of airtightness, drylining should be avoided unless great care is
taken. See right.
Similarly, timber floors are difficult to seal well
without a good deal of care. On the continent - and to an increasing extent in
the UK at large - concrete floor systems are being used for both ground and
first floors (often for other reasons such as acoustics, fire and the desire
for underfloor heating) and these are easier to make adequately airtight.
Hollow planks however can leak into cavities and require to be sealed at their
ends, this will dramatically improve air tightness
One
important and often quoted example is the timber first floor connection with a
block wall inner leaf. Who is responsible for ensuring absolute airtightness
when the timber joists rest on the wall and are infilled between with block and
mortar? Presumably the bricklayer, but is it then his fault if the timber is
installed at the wrong moisture level and subsequently twists and warps,
leaving cracks around every joint? Is it really feasible to attempt to tape or
mastic seal around them all, and what if the underside of the ceiling is to be
exposed? Far better perhaps, to do away with the joist-onto-wall detail altogether
and replace with joist hangers. Increasingly, the designer should be seeking
solutions which are intrinsically airtight because of the design, rather than
continuing as before while accepting an increased use of duck tape and mastic
on site! Whilst these may get you through the initial airtightness tests/air
leakage tests, they are short term solutions and not likely to lead to the
anticipated energy savings for the Client in the long term.
A good
review of the various materials and components which allow the Designer to
create an air barrier may be found in the BRE Report BR448: Airtightness in
Commercial and Public Buildings
7.4 Detailed Specification
Beyond the
performance specification illustrated earlier, it is important that the issue
of air tightness/air tightness testing becomes embedded within the standard specification
vocabulary.
Where an
equal or approved alternative may be allowed, it is critical that an
airtightness performance specification is part and parcel of that equality of
performance. For example, it may no longer remain satisfactory merely to
specify a membrane, but in addition to specify the fairly precise nature of the
sealing, overlapping and potentially the subsequent layers as well. Simply offering
a performance specification and ensuring the responsibility resides with the
Contractor is all very well, but it is important too to offer solutions that
will enable a satisfactory outcome to be achieved.
Design & Detailing for
Airtightness - Implementing Airtightness
In
addition to the intrinsic lack of airtightness, a problem of drylining is that
it can create hidden pathways for air, as above, into the void above suspended
ceilings and elsewhere throughout the building
Timber
joists built into a block wall - a poor detail for airtightness. Far better to
use joist hangars and avoid the problem. Source. Concrete planks are not free
of problems eitherhollow planks are often left ungrouted where they meet the
external wall, which could lead to extensive air leakage internally.
7.5 Implementing Airtightness
Key Principles
1.
The Contractor or Project Manager must be made
responsible for achieving the air tightness levels set. In particular, this
will involve careful co-ordination between trades; if this doesn’t happen then
an air leakage/air tightness failure will surely follow
2.
Inspection remains an integral part of achieving
air tightness and passing the air leakage test.
3.
Ideally at least 2 air leakage tests (air tightness
tests) will be undertaken; the first when the building is weather tight, and
the second air tightness test a couple of weeks or so before handover.
4.
Experience suggest that making one person (or team)
responsible for air tightness is the most effective way to tackle the issue.
5. Remedial air tightness works to existing
properties can reap substantial benefits without undue disruption.
It is not
yet generally possible within the UK to specify that a building shall be
airtight and leave it to the Architect or Contractor to sort out. There is not
yet a culture of airtight construction, except perhaps, amongst those who
construct superstores.
The
responsibility of the Designer in regards to the airtightness cannot be
overestimated, for if airtight buildings are to become main stream, as they are
elsewhere in the world, the techniques must be above all simple and buildable,
with most if not all of the ‘tricky’ areas designed out from the start. In this
way, such techniques can become ‘second nature’ to Contractors and there is
less reliance on potentially adversarial inspection and air leakage/air
tightness testing failures.
Ideally
too, the Designer will understand the issues sufficient to prepare a sound
performance specification – giving achievable targets for airtightness as well
as a clear description of responsibilities and procedures, and a clear and
practical set of overall and detail drawings, along with a detailed
specification.
In the
meantime, and even with good documents, there is likely to be a need for effort
and vigilance by both the Design Team and the Main Contractor or Project
Manager on site. This chapter briefly describes this effort, while the next
describes in more detail the actual air tightness testing procedures and
auditing techniques used.
7.5 Plan of Work
The RIBA
Plan of Work provides a framework for the entire design and construction
process. The table on the next page allocates specific tasks relating to
airtightness to each Work Stage to enable a schedule of tasks and
responsibilities for the Design team to be prepared according to each project.
7.6 Roles and Responsibilities on Site
Designer /
Design Team
The
responsibilities of the Design Team are detailed on the following page,
showing all stages including site works and beyond. Buildings usually comprise a number of different components,
creating a myriad of routes through which air can escape if not carefully
sealed at each and every junction. The Designer’s role is to simplify these
details to reduce difficulties on site.
It is
critical that the purpose of pursuing air tightness is explained so that all
concerned understand why they are being asked to attend to these issues. The initial
briefing of key personnel at mobilisation stage – whether or not this involves
the air tightness specialist – is also critical in determining the approach to
conducting the works, inspection, air tightness testing and auditing etc.
which will need to be dovetailed into the many other concerns on site.
On large
projects it may be useful for one member of the Design Team to take special
responsibility for air tightness / air leakage testing issues.
Contractor
The Main
Contractor’s principal responsibility is to deliver the air tightness
performance overall and the most likely task on any but the smallest jobs will
be that of co-ordination between the subcontractors. The Main Contractor must
be clear that he carries responsibility for the overall air tightness and in
turn must ensure that all subcontractors are clear about the extent of their
responsibilities. This is important since there may be some deviation to
conventional practice in order for air tightness to be achieved. It is always
prudent to place someone in the site team who has experience of air leakage/air
tightness on their previous projects as their experience may avert a potential air leakage/air
tightness failure
RIBA
Work Stage Design Team Tasks
A Appraisal Establish appropriate air
permeability rate
B Feasibility / Briefing Note
Microclimate
Test
existing buildings / building to be refurbished
Identify
procedure for review and testing
C Outline proposals Consider a/t issues
in relation to decisions about form of construction
Identify
zones and layers
D Detailed Proposals Identify
requirement of additional consultants / design by specialists
E Final Proposals Ensure co-ordination
between DT to ensure a/t envelope & penetrations
Detailed
application of airtight materials, junctions, service penetrations
F Production Info Select sub-contractors
for specialist works (incl. testing)
Careful
specification of components, membranes, materials
Emphasise
methods for airtightness on documentation
Careful
specification of components, membranes, materials
Emphasise
responsibilities in specification for dealing with ‘loose ends’ between
sub-contractor interfaces
G Tender Docum’n Define Contractors’
responsibilities for co-ordinating work sequences
H Tender Action Ensure selected tenders
include adequate airtightness procedures
J Mobilisation Brief all involved in
areas critical to air infiltration before work starts
Preparation
of samples, training, testing and QA procedures
K-L Site Works Co-ordinate inspection with
Building Control if required
Ensure
inspection of areas to be covered
Ensure
audits and testing schedule is adhered to
Ensure
design changes do not compromise airtightness performance
M Post Completion Obtain feedback from
concerning comfort and energy consumption
Carry
out remedial work as required at end of DLP.
As with
the Design Team, experience suggests that the best performance has been
achieved by Contractors who employ a dedicated individual (or team) to carry
responsibility for airtightness/air leakage, to inspect the works and instruct
as required.
For
Contractors, the issues of airtightness/air leakage are intimately linked to
issues of good or bad workmanship in general and this can make the issue both
more sensitive, but also more difficult to control. Even simple buildings are
immensely complex and so the most important aspect of all is the creation of an
overall culture of careful, tidy, accurate and airtight construction,
something which cannot be simply forced through with a performance
specification.
It is easier
to specify and draw an airtight detail than to build it, and so the emphasis on
inspection and Contractor responsibility has not developed from a prejudice
against Contractors, but from a realistic appreciation that this issue cannot
be entirely resolved ‘on paper.’ It is genuinely about a culture shift (at
least for many in the industry) and this is where the real challenge lies. Once
this shift is adopted there will be a far higher percentage of companies
passing their air leakage/air tightness testing at the first attempt
7.7 Inspection
Air
leakage found in dwellings according to studies undertaken by BRE. The studies
offer a range of conclusions, the most significant of which is that the
greatest volume of air leakage is occurring in areas out with the ‘normal’
consideration of ventilation, through the myriad of cracks and openings all
over the building which is described as ‘background air leakage.’
Of the
background air leakage subsequently investigated, the principal air leakage
routes were noted as being:
• Plasterboard dry lining on dabs or battens, often linked to
routes behind skirtings etc.
• Cracks and joints in the main structure; open perpends,
shrinkage & settlement cracks
• Joists penetrating external walls, esp. inner leaf of
cavity walls